FERC Rules to Reform Transmission Planning and Cost Allocation
On July 21, 2011, the Federal Energy Regulatory Commission (FERC) approved Order No. 1000, a final rule to reform its transmission-planning and cost-allocation requirements to benefit consumers by enhancing the grid's ability to support wholesale power markets and ensuring transmission services are provided at just and reasonable rates.
Order No. 1000 requires public utility transmission providers to improve transmission-planning processes and allocate costs for new transmission facilities to beneficiaries of those facilities. It also requires public utility transmission providers to align transmission planning and cost allocation. These changes will remove barriers to development of transmission facilities. Approved after considering more than 200 sets of public comments, Order No. 1000 builds on FERC's open access reforms of Order No. 888 (1996) and the planning reforms of Order No. 890 (2007).
The transmission-planning requirements established in the rule include development of regional transmission plans, consideration of transmission needs driven by public-policy requirements established by state or federal laws or regulations, and coordination between pairs of neighboring transmission-planning regions.
The cost-allocation requirements established in the rule include development of regional and interregional cost-allocation methods that satisfy certain principles. Under the rule, participant-funding of new transmission facilities is permitted but cannot be used as the regional or interregional cost-allocation method.
The rule also promotes competition in regional transmission-planning processes by removing from FERC-approved tariffs and agreements a federal right of first refusal for transmission facilities selected in a regional transmission plan for purposes of cost allocation, subject to certain limitations.
Order No. 1000 takes effect within 60 days of publication in the Federal Register. Transmission providers must make compliance filings on most issues within one year of the effective date. Interregional transmission coordination and cost-allocation compliance filings are required within 18 months of the effective date.
For more information, visit www.ferc.gov.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus