Resources

On Demand Media

Demand Viewing

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

White Papers

Designing Energy Services for Commercial and Industrial Customers

Over the past year, technology advances and high energy prices have stimulated interest in Advanced Metering Infrastructure (AMI). Discussions are wide-ranging. Some focus globally: Australian and Canadian “smart metering”, new European Union requirements, the results of time-of-use pilots that arose in the wake of California’s deregulation debacle.

More White Papers

Marketplace Ads

  • Trip Wire

    Automate NERC Cyber Security Compliance

  • Ike Blog

    Reports From The Front

Case Studies

York Region Finishes Tasks Faster

We all know that data integration improves productivity and York Region is living proof. Using AutoCAD® Map 3D, York saved time and money by relying on its AutoCAD-trained staff to quickly implement a new system that incorporates both CAD and GIS.

Save Time with CAD and GIS Integration

Read how the Public Works Department of the City of Tacoma (Tacoma), Washington, uses its geospatial data to do everything from issuing building permits and managing waste water to maintaining streetlights


         Subscribe in NewsGator Online   Subscribe in Bloglines

Holding down costs

Worldwide, developing countries have come to the conclusion that electricity is essential for the growth of their industry and commerce. At the same time, investing in electrification is a social responsibility that must be handled prudently to gain the most from utility investment in new infrastructure. We are seeing a trend worldwide to electrify regions that have never had access to reliable service. South Africa is only one such country with this desire to build out distribution to reach unserved areas.

The South African utility, Eskom, has electrified 3.3 million households over the past 11 years. From 1995 to 2000, 300,000 connections per year were made. The costs were borne by Eskom as a social investment. This represented around 200 projects running simultaneously with around 1000 transformer-zone designs that had to be investigated and approved by Eskom.

In order to achieve this ambitious plan with around eight staff members, it was critical that we develop indicators to help us determine target costs per connection. Good indicators enabled us to compare the cost-effectiveness of our engineering designs needed for the massive expansion of our distribution system. Without indicators, we found it impossible to select a strategic direction with optimal transformer zone designs to enable Eskom to meet the electrification challenge.

A FEW NUMBERS

The table provides a few examples of our distribution indicators as a function of region, which provides Eskom personnel targets for which to aim. (The indicator values listed are pertinent to South Africa and may not suit all conditions.)

Eskom personnel were provided guidelines that directly impacted the cost to serve. Areas addressed include:

  • Average span length

    Present structures are designed with a factor of safety of 4.5 to cater to 150-m (492-ft) spans, often with hare conductor.

  • Methods to minimize angle structures

    Checks are routinely made to assure that direct routes are selected where possible.

  • Bare-wire low voltage (LV)

    If the customer density is low, bare-wire LV should be considered.

  • Average span length for ABC conductor

    This should be around 60 m (197 ft) at a minimum.

  • Average utilization of angle structures

    We expect to increase utilization of pole capacity from 20-30% to 60%.

  • Total transformer capacity/number of connections

    This ratio is to check whether the transformer capacity suits the stated average diversified maximum demand design.

  • Material cost as a portion of total cost

    This is an indicator of efficiency. It should be around 0.6.

  • Number of connections per pole top

    In high-density areas this should be around 6 or 8; in lower-density areas, a figure of 4 or 2 might be acceptable.

  • Single-phase connections as a ratio to three phase

    Single phase must be considered as a first option, with reasons given if it is rejected.

PRODUCTIVITY INCREASE

Prior to developing our indicators, we found that individuals were floundering with an extremely high workload, but without a clear vision of what steps to take along the electrification road. Now we find that with an approved set of objective indicators, our designs are rarely rejected. Our consultants are also more productive as they understand more clearly what is expected of them from Eskom Distribution.

Prior to the use of indicators, connections typically cost 2000 rand (US$300) but climbed to the region of 4000 rand to 6000 rand (US$1000) as services were provided to more rural areas with population densities dropping from 1200 households/km2 (463 households/miles2) or greater to 30 households/km2 (11.58 households/miles2). With the use of indicators, we have reduced the costs per connection by more than 50% in real terms in the period from 1995 to 2000, in spite of electrifying deeply rural areas. This process has continued with funding from the government, although differences in priorities and requirements have led to an increase in costs in the last three years.


Rob Stephen is responsible for the Capital Programme in Eskom Distribution, and advises on technical aspects. stepherg@eskom.co.za

Distribution Indicators
Electrification Targets Region 1 Region 2 Region 3 Region 4
Connection cost (rand) 3084 2824 2554 2827
Cost per km (rand) 53,541 57,410 65,049 59,608
MVA per km 0.02 0.02 0.03 0.01
Transformer per km 0.42 0.31 0.56 0.47
Connections per km 22.56 24.80 32.33 24.83
Subtransmission infrastructure as a percent of total investment 21% 16% 19% 14%
These costs are indicative only. Actual costs at present could vary widely.

Want to use this article? Click here for options!
© 2008 Penton Media Inc.

Most Read

Community

Hurricane Ike Coverage

Hurricane Ike Coverage
On September 12th, Hurricane Ike tore through the Gulf Coast, wreaking havoc on lives and property. Transmission & Distribution World’s Rick Bush is headed to the region to provide a first-hand account of the damage including an insider view of utility emergency-response efforts. His reports and subsequent feature coverage will highlight how utilities, contractors and suppliers work as a team to restore power as quickly as possible.
Read Rick’s Blog, Ike: Reports from the Front

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

Webcasts

ACSS and HS285 Extend Grid Capacity

Sponsored by Southwire

There are capacity bottleneck situations, where new overhead transmission line construction is not a practical reality. In some of these situations overhead lines are in place and they are not able to provide the transfer capacity needed.

Register Now!


Supercondutor Cable Systems

Sponsored by American Superconductor

Transmission & Distribution World presents Superconductor Cable Systems, A Part of the Increasing Bulk Power Transfer Series.

Register Now!


Evolution of Next Generation Wireless Communications in Power Delivery

Sponsored by Alcatel-Lucent

Evolution of Next Generation Wireless Communications in Power Delivery - seeing wireless communications solutions emerge to enable more efficient operations.

Register Now!

More Webcasts

Featured Activity

T&D World University 2008

Get expanded education, practical experience and unprecedented networking in 3 days at T&D World University, the Continuing Education Program for Utility Management, Engineers and Technical Professionals. October 27-29, 2008, Dallas, TX. With CEU-Earning Seminars, Specialized Tracks, 59+ Courses, T&D allows you to maximize your time, with minimal work interruptions. Bring your team to this productive learning environment.

Jobzone
  • October Issue
  • September Issue
  • August Issue
  • July Issue
  • June Issue
  • May Issue
  • April Issue

Browse Back Issues