Resources

Search, compare, and request quotes for nearly 13,000 products with detailed listings:

Blogs

  • 2012 IEEE PES Show Blog

    The IEEE Blog is a unique tour of the 2012 PES Expo in Orlando, FL, by Gene Wolf, former chairman of the IEEE PES T&D Committee.

White Papers

» More White Papers

Follow Power Editor Nikki Chandler on

Follow Technology Editor on Vito Longo

Find T&D World on Facebook

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

  
   

Blackout: Shocked Into Action

THE BLACKOUT ON AUGUST 14, 2003, WAS THE LARGEST IN U.S. HISTORY. It started with a line going out in Ohio. It affected eight U.S. states and one Canadian province. It covered more than 9000 sq miles (23,310 sq km). It disrupted over 61,000 MW of power. It caused three deaths. It closed 12 major airports. It touched more than 50 million people ¡ª one-third of the Canadian population and one-seventh of the U.S. population. It cost more than US$4 billion in lost economic activity.

As part of the postmortem to this event, the joint Department of Energy (DOE) and Federal Energy Regulatory Commission (FERC) report to Congress in February 2006 stated that the blackout was ¡°caused in part by deficiencies by the system that monitors the electric grid and a lack of awareness of deteriorating conditions by the operators who monitor the system.¡±

Among the report recommendations are that:

  • North American Electric Reliability Council (NERC) should evaluate and adopt better real-time tools for operators

  • NERC, FERC and Canadian authorities should require the use of time-synchronized data recorders

  • FERC and Canadian authorities should establish requirements for the collection and reporting of data needed for post-blackout analysis.

The blackout focused attention on the need for real-time wide-area visibility and situational awareness. None of this can be done without monitoring across the national grid.

THE RESPONSE


In October 2003, just two months after the blackout, the DOE gathered together a small group of utilities, vendors and universities. This group has become the nucleus of the Eastern Interconnect Phasor Project (EIPP). Entergy, New York Power Authority (NYPA), Tennessee Valley Authority (TVA) and American Electric Power (AEP) are the founding utilities of EIPP.

The purpose of the 2003 meeting was to begin defining new methods to mitigate effects of future system disturbances. The vision of EIPP is to improve power-system reliability through wide-area measurement, monitoring and control.

Almost three years later, EIPP now has more than 100 utility and nonutility participants. During the past three years, the EIPP task teams have taken the Eastern grid from a place with virtually no phasor measurement units (PMUs) to a grid with more than 75 planned or implemented PMUs. Now that EIPP has the infrastructure in place, over the next several years it will focus on the areas of visualization tools, planning, communications infrastructure, protection and switching, and grid monitoring.

BENEFITS OF PMU DATA


A combination of trend analysis and post-disturbance analysis will broaden the overall understanding of the Eastern Interconnect power-system dynamics. PMU data can be used to calculate the frequency-response characteristics for a generator trip, the oscillatory modes and associated damping, identification and analysis of voltage swings. Trending analysis can be done in terms of correlating with time of day, season, peak, load and so forth. The knowledge gained from this analysis can be used for developing transmission-operating procedures and reinforcement plans.

One of the major lessons learned from the 2003 blackout was the importance of having time-synchronized system-data recorders. In the absence of these, it was very laborious to put together the events and sequences that occurred across the Northeast and at several utilities that led to the blackout. Hence, recommendation 28 of the joint U.S.-Canada task force investigating the blackout was: Require use of time-synchronized data recorders.

A great advantage of PMU data is that because it is time-synchronized and has a high sampling rate, it can be used for measuring the phase-angle difference between two buses. This improves a utility's ability to monitor grid dynamics and stability for reliability management. This level of information was never available before, and the potential to monitor and manage the system was not possible before. All of these benefits will be significant steps in enhancing the reliability of the grid.

ENTERGY PHASOR MEASUREMENT SYSTEM


At the time of the August 2003 blackout, Entergy, like most utilities in the Eastern Interconnect, did not possess any PMUs on its transmission grid. Today, Entergy maintains one of the newest and largest PMU systems in the Eastern Interconnect. The Entergy PMU system is dispersed across four states and is recording on the 115-kV/138-kV, 230-kV and 500-kV transmission levels.

Entergy's 15 current PMU sites were selected based on the need to monitor important interfaces and possible instability areas of the Entergy system. Site selection also depended on availability of Entergy-owned fiber and bandwidth. None of the existing sites use leased fiber. Several sites were eliminated as possible candidates because fiber and bandwidth were not available or too costly to employ. Entergy currently has a siting study underway to select future sites based on the need for redundancy, monitoring and control of the Entergy grid.

COMMUNICATIONS


Entergy's internal communication design for the Entergy phasor system used expertise from various Entergy departments, SAIC and OSIsoft. The idea was that a dual phasor data collector (PDC) design could deliver all internal requirements, while also satisfying the external requirements, all in a secure fashion. An internal server on Entergy's corporate network would poll PMUs and also service internal requests via OSI's Processbook client application. A second external server would sit in Entergy's demilitarized zone (DMZ) to synchronize data with the internal server, and also send and receive data with TVA via the virtual private network (VPN). Open protocol communication (OPC) was chosen to share phasor data with TVA. While it is based on Microsoft's Distributed COM (DCOM) standard, it enables open standards communication without having to resort to a proprietary solution.

This design provided a server to share data externally without having to allow that server access to the internal network to poll the meters. Furthermore, as there is also an internal server, Entergy still has access to its own phasor data in the event of external server loss. Because of how OSIsoft's Pi synchronizes data, there are no issues about how the external server receives data from the internal server. All data synchronization occurs via the Pi-to-Pi interface and is initiated internally.

In January 2006, Entergy's PMU stations, previously on the corporate network, were migrated to a newly designed, private, secure, Entergy-owned fiber network used solely for critical data. Phasor data is viewed as controls-type, critical data. As such, this private network allows for more stringent access privileges to the PMU data, including restricted access privileges to both the servers and PMUs. The figure above is a high-level view of how the new communications network will deliver phasor data.

PHASOR DATA COLLECTOR


The Arbiter meters use software in the form of the Arbiter Interface from OSIsoft to pass data from the substation to the PI UDS system or PDC. The Pi system then stores the data on servers for multiple days. The PMUs, as well as the Pi interface, now support 37.118 communications protocol, which requires a minimum data-sampling rate of 30 samples/sec.

From Entergy's internal PDC, all data points are exported via multiple instances of the Pi-to-Pi interface to an external PDC, which resides on the Entergy DMZ. OPC Server software is installed on the DMZ server to allow TVA access to the data. A software package from Matrikon, called the OPC Tunneller, is used to automatically configure DCOM settings and enable reliable OPC communications over differing domains or work groups.

FIELD IMPLEMENTATION


The project used Entergy personnel to perform the field installations of the PMUs. In addition to the communications considerations for a potential PMU site, several other steps preceded PMU installation. For instance, after Entergy's System Planning and Operations identified the transmission lines to be monitored, Substation Design identified a potential transformer and current transformer from which to collect PMU data. From various station drawings, System Planning verified the selection of input locations. Since many of the PTs and CTs selected for monitoring have been in service for years, each device was field inspected to verify that they are both in service, appear physically sound and match drawings. Since all of our substations are in constant service, a hands-on inspection was not always possible. Also, the project coordinator, Entergy field personnel and relay design made a site visit to each location. Information verified included: adequate physical room in control house, availability of rack space for Arbiter meter, visual of selected PT and CT, and availability of dc power.

ACKNOWLEDGEMENT


The Entergy phasor system reflects the most current, state-of-the-art understanding of phasor measurements. This system is a reality because of the dedication, efforts, hard work and courage of the Entergy Phasor Project Team. I am honored to work with such an incredible group of individuals.


Floyd Galvan, a licensed professional engineer in Texas, is a senior project manager for Research & Development at Entergy Corp. His areas of specialization include phasor measurement and control, grid visualization, applications of phasor measurements, long-term planning and regional energy pricing. Galvan has worked throughout the industry in various areas including system planning, fuels procurement and wholesale energy forecasting. He has held leadership positions within the DOE EIPP and CEATI, and has served on numerous panels and committees at the NSF. He received a BSEE degree from Texas A&M University-Kingsville and a master's degree in liberal arts with an art history focus from Southern Methodist University. FGalvan@entergy.com

PMU Locations in the Entergy System
¡ï Existing PMU locations ¡ï New PMU locations
10 sites are operational
5 sites came on-line summer of 2006
PMU ¡ª Arbiter 1133A, Power Sentinal
PDC ¡ª OSIsoft PI Historian

EASTERN INTERCONNECT PHASOR PROJECT PARTICIPANTS
Manufacturer participants in the EIPP include:
ABB General Electric Patrick Engineering
Ametek Gemscape Power Measurement
Arbiter Global Energy PowerWorld
AREVA InStep Psymetrix
Bigwoods Systems Macrodyne Qualitrol
Ciber MCGWare SEL
Concurrent Technologies Corp. Mehta Tech Siemens
Cyberpower NxtPhase SISCO
Doble OSIsoft V&R Energy
Researchers and organizations supporting EIPP efforts include:
Arizona State University EPRI NYSERDA
AWEA Georgia Tech Rensselaer Polytechnic Institute
CEA KEMA Texas A&M University
CEC Michigan Tech University of Wyoming
CERTS Montana Tech Virginia Tech
Cornell University Navigant Washington State University
Department of Energy NIST West Virginia University

Ongoing Work in Phasor Measurements at Entergy and in the Industry
Projects Participants
Integrating phasor measurements into state estimation, Phase II AREVA, TVA, Entergy, PG&E, Manitoba Hydro, Idaho Power, ORNL, Northeastern University, Washington State University, First Energy
Transmission line dynamic ratings using PMUs Entergy, NEETRAC/Georgia Tech, TVA
Detection, prevention and mitigation of cascading events using PMUs prototype implementation at TVA and Entergy PSERC, Entergy, TVA, AREVA, ATC, EPRI, Korean EPRI, Texas A&M, Washington State University, Arizona State University
Distributed state estimation with application to alarm processing CTC, Georgia Tech, Entergy, METC, NYPA
Placement and benefits of phasor measurement units for monitoring and control of the Entergy grid Northeastern University, Entergy
System security using phase-angle differences Entergy, Washington State University
Wide-area real-time frequency visualization and location of disturbance EPRI, Entergy, TVA, Virginia Tech

WHAT IS PHASOR DATA?


Want to use this article? Click here for options!
© 2012 Penton Media Inc.


Acceptable Use Policy

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.

General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.

blog comments powered by Disqus

T&D TV

Most Read


Find Other Popular Items

Features

Vegetation Management
Grid Optimization

Upcoming Webcasts

Transmission & Distribution World allows you to access live and on-demand webcasts. Webcasts are available during their scheduled date and time. If you are unable to attend at the scheduled time, these free events will be available On-Demand for viewing at your convenience.


On-Demand Webcasts

» View More Webcasts

Jobzone
  • Transmission & Distribution World May 2012 Issue
  • Transmission & Distribution World April2012 Issue
  • Transmission & Distribution World March 2012 Issue
  • Transmission & Distribution World February 2012 Issue
  • January 2012 Issue
  • December 2011 Issue
  • November 2011 Issue

Browse Back Issues