Resources

On Demand Media

Demand Viewing

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

White Papers

Moving Toward Utility-Scale Deployment of Dynamic Pricing in Mass Markets

Prior studies have shown that dynamic pricing can provide numerous benefits to utilities and customers alike.

A Deployment Strategy for the Smart Grid: From the Generator to the Refrigerator

This white paper describes a coordinated, prioritized and customer-based development strategy for utilities considering the Smart Grid initiative.

A Guide to Transformer Winding Resistance Measurements

Matz Ohlen and Peter Werelius of Megger discuss the unique method of winding resistance measurements in transformers and how they are a fundamental importance to detecting potential mechanical and electrical problems that other methods are unable to detect the field.

Smart Metering for Water Utilities

Should water utilities replace current consumption meters with “smart metering” systems that provide more information to both utilities and customers? This question is being hotly debated in today’s electric utility industry but currently appears to be of less interest in the water industry.

Gene Kim's Practical Steps to Achieve and Maintain NERC Compliance

Gene Kim, CTO of Tripwire, describes seven practical steps owners and operators of the bulk power system can take to meet the mandatory NERC-CIP standards, helping them avoid huge fines for non-compliance and protect North America’s bulk power system.

More White Papers

Marketplace

Trip Wire

Automate NERC Cyber Security Compliance

Reports from Spain Blog

Electric Solar: Reports from Spain


         Subscribe in NewsGator Online   Subscribe in Bloglines

Reconstructing Iraq

WE LEFT THE GREEN ZONE, HEADING FOR THE BAGHDAD AIRPORT IN A HIGH-SPEED DASH along a highway known as Route Irish. Adrenaline pumped through our veins on this 130°F (54°C) day as we set off on what is considered the most dangerous road in Iraq. I was traveling in the middle vehicle of a three-car security detail, referred to as a CP (close protection) team. The lead car carefully checked ahead for terrorist threats and roadside bombs. The rear vehicle was on the watch for suicide bombers.

We found ourselves backed up in traffic behind a slow-moving U.S. military convoy patrolling the road, making us an even easier target for potential bombers. The security team in our car became more agitated than I had ever seen them before. Jalal, our head Iraqi guard, was driving with one hand while holding a handgun in the other. George, the head of our security operation, sat next to him with an AK-47 submachine gun in one hand and a radio in the other, telling everyone in our CP to keep away from any car with a sole driver. I was in the back seat; my heart was pounding.

Just as traffic began to ease up, our car jolted forward. Behind us, two cars were in flames — a suicide bomber had struck. We all escaped, shaken but unharmed. Sadly, only two weeks later, Jalal died in another suicide bombing on that very same road.

I was in Iraq working with one of the many international contractors who started reconstruction work in the fall of 2003. At that time, there was a positive vibe, and I had every expectation that the situation in Iraq would improve as U.S. reconstruction efforts took hold. Instead, it got worse by the day.

RECONSTRUCTION DETAILS

USAID and the US Army Corps of Engineers administered the majority of the reconstruction efforts at this time and appointed U.S. contractors to manage the bulk of the power-grid reconstruction projects. We won our first subcontract to rebuild 130 km (81 miles) of a critical 400-kV transmission line that fed power to Baghdad from thermal power stations in the south. The majority of the towers on this line had been pulled down by the Iraqis after the war, and they needed to be completely reconstructed.

TIGHT DEADLINES REQUIRE AGGRESSIVE MEASURES

In order to meet incredibly tight deadlines, we were forced to transport almost everything to the construction site by air. This included 1000 workers as well as tower steel, insulators and tension-stringing equipment. Ultimately, we chartered more than 40 flights from India, Africa, the Middle East, China and the United Kingdom. Finding the pilots and planes willing to fly into Iraq was not easy. The pilots, mostly Ukrainian, were incredibly brave, often landing their aircraft in the most dangerous locations.

Just as our work commenced, the rainy season arrived, turning the Arab marshlands into a quagmire. We couldn't get our vehicles to the tower sites and often had to carry tower steelwork by hand through knee-deep water. With 1000 security personnel working alongside us to protect us from attack, we were able to get the 130 km of line back up within four months of signing the contract, a miracle considering the circumstances. We were awarded subsequent jobs and have since completed an additional six transmission reconstruction projects in Iraq.

WORKING WITH IRAQIS

We worked with each of the ethnic groupings in Iraq — Sunni, Shia and Kurd. They are all very proud, tough and resilient. At a personal level, they are great people who will adopt you as a friend. However, at a nationalistic level, I felt a deep resentment toward us being there. Working across the country highlighted the divisions that exist in Iraq. For example, we could not use Sunni or Shia workers in the Kurdish north. Shia or Kurds could not work west of Baghdad in the Sunni Triangle, and in the south it was preferable to use Shia. We also learned that conflicts exist within the ethnic groupings as we witnessed armed battles between tribal villages living near the transmission lines.

The insurgency has certainly stifled reconstruction efforts, as has the rapid growth in the demand for power. However, it is disappointing that far too many of the U.S.'s accomplishments in the rebuilding of Iraq's infrastructure have gone unnoticed. Those of us who are involved in these efforts are proud of the progress that has been made under some of the most challenging circumstances imaginable.


Paul Hinks is now the CEO of U.S.-based Symbion Power and continues to be involved with Iraqi reconstruction projects. paul.hinks@symbion-power.com

Want to use this article? Click here for options!
© 2009 Penton Media Inc.

Most Read

Community

Connecting Solar to the Grid

Electric Solar: Reports from Spain
Rick is joining a U.S. contingent traveling with the Solar Electric Power Association to tour large-scale grid connected solar installations in Southern Spain. Check out Rick’s daily blog and experience the world of solar that is in the here and now.
Read Rick’s Blog, Electric Solar: Reports from Spain

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

Webcasts

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

ACSS and HS285 Extend Grid Capacity

Sponsored by Southwire

There are capacity bottleneck situations, where new overhead transmission line construction is not a practical reality. In some of these situations overhead lines are in place and they are not able to provide the transfer capacity needed.

Register Now!


Supercondutor Cable Systems

Sponsored by American Superconductor

Transmission & Distribution World presents Superconductor Cable Systems, A Part of the Increasing Bulk Power Transfer Series.

Register Now!

More Webcasts

Jobzone
  • June 2009 Issue
  • May 2009 Issue
  • April 2009 Issue
  • March 2009 Issue
  • February 2009 Issue
  • January 2009 Issue
  • December 2008 Issue

Browse Back Issues