Siemens to Expand Power Supply Network in the UAE
Siemens Energy has received an order worth approximately 30 million euros from Dubai-based Federal Electricity and Water Authority (FEWA) as part of power supply network expansion. The order from the United Arab Emirates (UAE) covers the supply of a turnkey substation in Fujeirah, one of the northern emirates.
Four substations will also be modernized. The power supply project is scheduled for completion within 15 months.
The turnkey substation for the 132- kV and 33-kV voltage levels will be supplied together with Siemens transformers, protection equipment, and instrumentation and controls. It will be erected in the town of Qidfa in the emirate of Fujeirah and will in the future strengthen the power supply network in the north of the UAE. Four existing substations will also be modernized in the neighboring emirates of Ras-al-Kaimah and Ajman.
In total, Siemens will supply 10 bays 132-kV and 63 panels 33-kV for gas-insulated switchgear as well as two 90 MVA transformers from its production plants in Berlin, Dresden and Frankfurt.
Visit www.siemens.com to learn more.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus