Resources

On Demand Media

Demand Viewing

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

White Papers

Moving Toward Utility-Scale Deployment of Dynamic Pricing in Mass Markets

Prior studies have shown that dynamic pricing can provide numerous benefits to utilities and customers alike.

A Deployment Strategy for the Smart Grid: From the Generator to the Refrigerator

This white paper describes a coordinated, prioritized and customer-based development strategy for utilities considering the Smart Grid initiative.

A Guide to Transformer Winding Resistance Measurements

Matz Ohlen and Peter Werelius of Megger discuss the unique method of winding resistance measurements in transformers and how they are a fundamental importance to detecting potential mechanical and electrical problems that other methods are unable to detect the field.

Smart Metering for Water Utilities

Should water utilities replace current consumption meters with “smart metering” systems that provide more information to both utilities and customers? This question is being hotly debated in today’s electric utility industry but currently appears to be of less interest in the water industry.

Gene Kim's Practical Steps to Achieve and Maintain NERC Compliance

Gene Kim, CTO of Tripwire, describes seven practical steps owners and operators of the bulk power system can take to meet the mandatory NERC-CIP standards, helping them avoid huge fines for non-compliance and protect North America’s bulk power system.

More White Papers

Marketplace

Trip Wire

Automate NERC Cyber Security Compliance

Reports from Spain Blog

Electric Solar: Reports from Spain


         Subscribe in NewsGator Online   Subscribe in Bloglines

Lessons Learned from Rita Helps Entergy Texas Prepare for 2006 Hurricane Season

With hurricane season approaching, Entergy Texas is using the many lessons learned from Hurricane Rita to strengthen storm-response capabilities. More than 286,000 Entergy Texas customers were left without power following Hurricane Rita’s landfall last Sept. 24. The company serves 380,000 customers.

“Entergy restored power to all customers who were able to take electricity in 21 days,” said John Mullins, distribution operations director. “In addition, we learned several new things about storm response during what was the most devastating event in Entergy Texas history.”

The company suffered extensive damage following Rita, which severed all transmission connections between Louisiana and Texas. In Texas alone, nearly 10,000 distribution power poles were downed, many snapped in half. Power generating units at Lewis Creek near Conroe and Sabine Station near Bridge City were also taken off line by the storm, with the Sabine plant suffering extensive damage.

Restoring power after the storm cost the company about US$400 million.

Since Rita, however, company workers have made repairs and fully restored Southeast Texas’ electrical system. Additionally, improvements are planned for the logistics of power restoration should another storm strike, and upgrades have been made to key electronic equipment in the company’s distribution operations center.

Mullins said the company has repaired all known storm damage that could affect the reliability of the electrical system and performed visual patrols of primary circuits. Texas employees are continually monitoring rights-of-way for dead trees inside or outside the right-of-way that could fall into lines and disrupt service. “When we discover trees outside our rights-of-way that could present a threat, we are working with landowners on removal in order to prevent outages,” Mullins said.

Mullins said lessons learned from Rita will be incorporated into storm drills this year as part of testing the various response systems within the company.

Mullins cited several positives that came out of Rita. One involved the use of helicopters to perform aerial assessments immediately after the storm. “Using helicopters was much faster than other types of patrols,” he said. “It helped expedite repairs.” Mullins also cited coordination with industrial customers to get the many plants in Southeast Texas back on line. “Getting plants back up was critical to our success,” he said.

Mullins said many lessons were learned in the area of logistics. Before the storm struck, 4000 personnel were pre-staged to respond to the storm. The workforce swelled to more than 10,000 workers once restoration began. The size of the workforce, made up of electrical workers from around the country, made it possible to restore power quickly. Mullins said that Rita proved that getting major logistical arrangements--hotels, motels, food, etc.--lined up before crews arrived was critical when receiving an army of people.

In addition to completing repairs before the new hurricane season arrives, Entergy Texas has also upgraded its Automated Mapping and Facilities Management system. The technology is used in the Distribution Operations Center (DOC) at Edison Plaza and provides instant information regarding the status of equipment throughout Southeast Texas. It is also used to dispatch workers when outages occur. DOC Manager Gerald Jones said features have been added that improves the efficiency of the company’s dispatching system.

Want to use this article? Click here for options!
© 2009 Penton Media Inc.

Most Read

Community

Connecting Solar to the Grid

Electric Solar: Reports from Spain
Rick is joining a U.S. contingent traveling with the Solar Electric Power Association to tour large-scale grid connected solar installations in Southern Spain. Check out Rick’s daily blog and experience the world of solar that is in the here and now.
Read Rick’s Blog, Electric Solar: Reports from Spain

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

Webcasts

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

ACSS and HS285 Extend Grid Capacity

Sponsored by Southwire

There are capacity bottleneck situations, where new overhead transmission line construction is not a practical reality. In some of these situations overhead lines are in place and they are not able to provide the transfer capacity needed.

Register Now!


Supercondutor Cable Systems

Sponsored by American Superconductor

Transmission & Distribution World presents Superconductor Cable Systems, A Part of the Increasing Bulk Power Transfer Series.

Register Now!

More Webcasts

Jobzone
  • June 2009 Issue
  • May 2009 Issue
  • April 2009 Issue
  • March 2009 Issue
  • February 2009 Issue
  • January 2009 Issue
  • December 2008 Issue

Browse Back Issues