DTE Energy Considers Distributed Generation
Richard Seguin is principal engineer, distributed resources, system planning and engineering for Detroit Edison. He has 35 years of experience in electrical system planning, design and operation. Since 2002, he has installed 18 distributed generation projects on the Detroit Edison system totaling nearly 9 MW. He holds a BSEE degree. SeguinR@DTEenergy.com
William J. Steeley is a senior project manager in distributed resource and energy storage at EPRI. His work experience also includes 24 years at PG&E in transmission planning and in PG&E's R&D department where he was project and program manager for various generation and T&D projects. He holds BSEE and MSEE degrees from Ohio State University and is a registered professional engineer in California. WSteeley@epri.com
In these early applications, DTE Energy learned several key lessons from early distributed energy resources (DER) applications:
One of the expectations of management was to make sure that DER projects made sense economically. Therefore, an important part of the DER economic evaluation, which compares traditional T&D solutions to DER solutions, is to compare appropriately. The cost of the DER alternative should not be based on the cost per kilowatt of capacity added, but rather compared to the cost to resolve the capacity shortfall problem.
For example, consider the cost to build a new substation for an area experiencing loading problems. A new 30-MW substation will cost around $6 million, which translates to a cost per kilowatt of $200. This will usually be cheaper than any DER alternative when factoring in the cost of buying DER. However, this assumes that one will be using the whole 30 MW immediately. Generally, most overloads are not 30 MW; they are more on the magnitude of 1 or 2 MW. The cost to resolve a 1-MW capacity shortfall problem with the same $6 million substation is $6000/kW. Now comparing this cost of a 1-MW DER alternative, approximately $450/kW, it begins to look very favorable for the “DER and Defer” strategy.
After DTE Energy integrated this new measure on all new capital projects, the next step was to develop a DER capital project budget. Although the DER and Defer strategy permits better economic use of resources, it is not the only reason to use DER. After a probability analysis is performed, it becomes apparent that the load will arrive before some T&D projects will be completed. DER can be a tool to help make sure that these projects are addressed even if the final T&D solution is years away. DER can become a planned budget line item to rescue the project when and if it cannot be done (storms, right-of-way, community approvals and faster-than-anticipated load growth). DER also can be used as a “Do Nothing” alternative in the capital project budget process. This becomes not only part of a project alternative analysis, but can be used as preplanned recovery plan.
There is another way to look at the economics of using DER. The purchase of a portable substation is not based on the need to facilitate maintenance or for the change-out of a transformer for one particular instance. It would not be possible to justify its purchase on that basis alone. The portable substation is justified on repeated use over time. This is the same rationale used to demonstrate the cost effectiveness for the purchase of DER.
The DTE Energy DER team arrived at this truism after a review of the economics of its first DER installation. This project involved the use of a leased portable generator in an emergency. Over the course of a subsequent economic evaluation, the team demonstrated that purchasing the DER was more economically sound than leasing one. Once a DER is purchased, the comparison is between the DER installation cost and the cost of traditional T&D cost.
In order for DER to be successful, it takes real management support. At DTE Energy, this support came from the highest levels, specifically the CEO and president.
This management support came in the form of naming a champion to shepherd the integration. In DTE Energy's case, a small DER planning group was established and given director-level reporting.
Although utility-owned DER is sometimes a cost-effective solution to a summer peak loading situation, it is not the only answer. There may be customer-owned generation on the circuit that can be used under a joint-use arrangement with the customer.
This must always be included in the site-selection process.
| Location | Day-to-Day Rating (amps) | Emer Rating (amps) | Peak Rating (amps) | 2002 Hours Above | 2003 Hours Above | 2004 Hours Above | 2005 Hours Above |
|---|---|---|---|---|---|---|---|
| Adair DC322 | 408 | 520 | 650 | 182 | 81 | — | — |
| Grosse Ile DC2841 | 500 | 636 | 684 | 45 | 3 | 40 | 234 |
| Shores DC1770 | 493 | 552 | 553 | 22 | 2 | 41 | 122 |
| Union Lk DC1688 | 524 | 760 | 860 | 265 | 55 | 188 | 410 |
| Wayne DC9435 | 577 | 789 | 636 | 27 | 9 | 24 | — |
| Milford DC8103 | 590 | 695 | 695 | — | — | 32 | 58 |
| Webster DC371 | 360 | 505 | 416 | — | — | N/A | 75 |
| Ivanhoe DC1760 | 600 | 720 | 760 | — | — | N/A | New in 2006 |
| Golf DC8518 | 450 | 630 | 647 | — | — | N/A | New in 2006 |
| Circuits with DER circuit support (peak amps value would be the overload without DER). | 26 Days over 90 | 3 Days over 90 | 2 Days over 90 | 20 Days over 90 | |||
EPRI and DTE Energy have recently published a report entitled Best Practices Guidebook for Integration of Distributed Energy Resources into Utility System Planning (product ID 1011250). This report provides, for the first time, a practical guidebook of industry best practices for integrating DER into the utility planning and operating process. The information presented in the report is based on DTE Energy's real-world experience in DER planning and implementation for distribution solutions and customer services.
The report includes key lessons learned, capital budget planning, financial calculations for engineers, planning and protection, system design, siting and approval, construction and in-commissioning, and methods of control and operation. It also presents five case studies of DTE Energy's DER-based distribution solutions.

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by DisqusWant to use this article? Click here for options!
© 2008 Penton Media Inc.










