Can We Achieve 20% Wind by 2030?
Regulators, developers and utilities worldwide have a lot riding on this question.
Renewable Energy Technologies have Matured as a Source of Electricity and have caught the attention of our industry. They are seen as the clean, emissions-free alternative to fossil fuels. Many also see renewables as an increasingly significant part of the resolution to the quandary of energy security and climate change facing the world today.
Worldwide, the need for energy continues to increase, while in India and China, energy growth has reached explosive proportions. Fossil-fuel supplies are becoming more expensive and more difficult to remove from the Earth. The Intergovernmental Panel of Climate Change's “Fourth Assessment Report” published in 2007 (latest year for data) identified the power sector as the single-largest source of greenhouse gasses, accounting for 38% of CO
According to a recent Worldwatch Institute report, more than 65 countries have national goals for accelerating the use of renewable energy and are enacting policies to achieve those goals. In 2007, USA Today reported the global capacity for photovoltaic equipment at approximately 9740 MW with projections of 12,500 MW by the end of 2008. The Earth Policy Institute in Washington, D.C. reported more than 10,000 MW of geothermal generation installed worldwide by the end of 2007. In 2008, the Global Wind Energy Council estimates the world's total wind-generation capacity at roughly 100 GW.
IT IS THE LAW
China's Renewable Energy Law, which went into effect on Jan. 1, 2006, was created to help China meet its goal of providing 15% of the country's electric energy from renewable sources by 2020. By the end of 2007, China had installed more than 6000 MW of wind generation and estimated its 2008 installed capacity would be about 9000 MW.
The European Union (EU) leads the world with installed renewable capacity. In fact, the 2001 EU Renewable Energy Directive encouraged the development of a renewable national policy. Overall, 2007 saw the EU generate approximately 3.7% of its electricity with wind power. With more than 56 GW of installed wind-generation capacity, the European Wind Energy Association reports the EU has set a binding target of generating 20% of its electricity from renewable sources by 2020 for its 27 members.
“Europe has had a long-term, stable policy for a decade, and it has given stability to their wind development,” said Charles Smith, executive director of the Utility Wind Integration Group. “The policy framework gives investment certainty, and has lead to significant investment in manufacturing capacity and interconnection of wind generation. They have interconnection queues in each country, but national laws require the utilities to connect the wind generators, reinforce the system if necessary and to do it quickly.”
By the end of 2007, 35 U.S. states were generating approximately 21 GW from wind power, which is about 1.5% of the U.S. electricity needs. In May 2008, the U.S. Department of Energy's (DOE) Office of Energy Efficiency and Renewable Energy released the report “20% Wind Energy by 2030: Increasing Wind Energy's Contribution to U.S. Electricity Supply.” Black & Veatch (Overland Park, Kansas, U.S.) analyzed the market potential for significant wind energy growth, evaluated the U.S. wind supply and developed cost-supply curves for the wind resources to establish the basis of this report. In addition, the DOE worked with the National Renewable Energy Laboratory, Sandia National Laboratory, the American Wind Energy Association and other wind industry partners to produce this extensive report.
The report found the United States has more than sufficient wind resources to generate 20% of the nation's electricity and that wind generation is affordable. The report stated, “The data suggest that as much as 600 GW of wind resources could be available for US$60 to $100 per megawatt-hour.”
“The wind technology exists. It doesn't requiring any major technological breakthroughs to reach this level of wind generation. It does require action,” said Steve Lindenberg, team leader, DOE technology applications. “The installation rate has to increase from 2006's 3 GW to more than 16 GW per year by 2018 and continue at roughly that rate through 2030. With the 5329 MW installed in 2007 and the projected 7500 MW in 2008, the United States is on track.”
IT IS POSSIBLE, BUT THERE ARE CHALLENGES
The DOE has identified several challenges to meeting the 20% goal. The United States needs a national renewable electricity standard (also referred to as a renewable portfolio standard or RPS), a national interstate transmission grid under the jurisdiction of the federal government and more transmission capacity. A RPS would signal a long-term national commitment to expanding the use of renewable energy. (Currently, 28 states and Washington D.C. have a RPS). But perhaps the biggest obstacle to increasing generation of any type is the process to install generation on the grid and a lack of available transmission capacity.
“We have a very dependable 57 Chevy, but we need an efficient, dependable 2009 vehicle to meet today's challenges,” commented Lindenberg.
WHEN THEORY AND REALITY MEET
In theory, we have an open-access system in each state for interconnection to the grid (Federal Energy Regulatory Commission [FERC] Orders 888 and 889). Unfortunately, when theory met reality, it did not mesh as well as expected. No one predicted the volume of the requests for interconnections from wind power producers. Also, the process takes a bottom-up approach. The interconnector files a request for service and pays the fee. The project then has to be studied, and each study is done individually. Network upgrades are determined for the specific project, with associated costs assigned to the project.
If the requestor withdrawals from the queue, the projects following the withdrawn project have to be restudied. In many cases, it becomes an endless loop of studies, restudies and more studies. As a result, it is not uncommon for interconnectors to file multiple requests to secure the least-cost position in a queue. This has added additional burden to an already overloaded system. The queues have become even more congested than the electrical transmission system. It is not unusual for a project to take three to five years or longer to work its way through a queue.
-
In February 2008, the Electric Reliability Council of Texas (Austin, Texas, U.S.) reported it had 222 projects representing approximately 100 GW in its interconnection queue.
-
By late April 2008, PJM (Norristown, Pennsylvania, U.S.) had 360 generation projects totaling 84.2 GW, the Southwest Power Pool (SPP; Little Rock, Arkansas, U.S.) had a queue of 106 projects representing over 26.8 GW, and ISO-New England had a queue of 104 projects representing about 13.4 GW.
-
California ISO (Folsom, California, U.S.) had 361 interconnection requests in its July queue totaling over 105 GW with more than 68 GW of renewable resources.
-
As of Oct. 31, 2008, the Midwest ISO (Carmel, Indiana, U.S.) had 408 (349 for wind) requests for interconnections totaling 82.7 GW (67.1 GW of wind) in its queue.
These projects represent substantial investments and significant amounts of generation, and they are not able to move forward on a reasonable schedule due to congestion.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus