Brazil Utility Upgrading Key Transmission Line
CPFL Piratininga, a power distribution unit of CPFL Energia, one of Brazil’s largest electric utilities, will install the 3M Aluminum Conductor Composite Reinforced (ACCR) to upgrade the capacity of a key transmission line serving a densely populated area in the state of São Paulo. The lightweight, sag-resistant 3M conductor provides more than twice the capacity of conventional steel conductors of similar size without requiring major tower modifications or construction of new towers.
CPFL Energia serves some 6.3 million customers in four states, with a generating capacity of 1,672 MW. With an expansion program underway to accommodate Brazil’s dynamic economic growth, the company expects to have 2,174 MW of capacity available in 2010.
The line to be upgraded with 3M ACCR passes through a residential neighborhood in Várzea Paulista, where houses lining both sides of the right of way present numerous costly logistical problems for building new towers.
Earlier in 2008, another major electric utility in Brazil, CTEEP, chose the 3M ACCR for a capacity upgrade under different circumstances. The utility is applying the conductor to avoid new tower construction in a rural area, on a line that crosses an environmentally sensitive section of the Paraná River.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus