American Transmission Co. Energizes New Power Line in Walworth County, Wisconsin
A new, 5-mile power line is energized and providing support to the electric system serving Walworth County, Wisconsin, according to American Transmission Co.
The new line, which runs between the Southwest Delavan Substation and the Bristol Substation on the northeast side of Delavan, represents a portion of a larger, multi-phase, multi-year project that will convert the electric transmission system in Rock and Walworth counties from 69,000 V to 138,000 V.
“These growing counties require a more robust system to accommodate the increasing usage and population,” said Charlie Gonzales, local relations representative. “The new system, which runs from north of Beloit to the Lake Geneva area, involves constructing new lines and modifying several substations and existing transmission lines to reinforce the network and ensure reliable service.”
According to Gonzales, the route along Interstate 43 was suggested by members of the public when ATC was considering potential routes. “With input from the community, we arrived at a route that could be supported by its residents and still meet our needs to reinforce the system in the area,” he explained.
Work continues on a segment through the city of Delavan and on a section between Delavan and Elkhorn, along with some work on the west end of the project. “We’re targeting next summer for completion and conversion to the higher voltage,” said Gonzales.
In addition to energizing the Southwest Delavan to Bristol line last week, the following work has been completed:
- Turtle to West Darien: Modifications have been completed on this existing 18-mile, 69-kilovolt line to allow for conversion to 138-kV. Aging wood poles and wires between the Turtle Substation near Beloit and the West Darien Substation on the southwest side of Darien were replaced with steel poles and new wires.
- West Darien to Southwest Delavan: This line, constructed mostly along new right-of-way, connects the West Darien Substation to a new Alliant Substation southwest of Delavan. Completed in 2007, the line currently operates at 69-kilovolts, but will be converted to 138-kV.

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by DisqusWant to use this article? Click here for options!
© 2008 Penton Media Inc.