California ISO OKs First Location-Constrained Transmission Project
The California Independent System Operator Corp. Board of Governors last week broke new ground in greening the grid by approving the Highwind Project transmission upgrade that will reach renewable generation facilities planned for a remote area of California.
The Highwind Project includes about 10 miles of transmission lines and a new substation in the Tehachapi area. It is the first project considered under new rules that allow the California ISO to designate a renewable energy resource area and allows Highwind to move forward under the Location Constrained Resource Interconnection (LCRI) process approved by the Federal Energy Regulatory Commission in late 2007. The LCRI process provides a way for the ISO to approve a project based on its ability to access remotely located wind, solar, geothermal or other renewable areas. And it sets up a cost recovery and project approval mechanism that breaks the “chicken-or-egg” dilemma.
“The remote areas in California with the most potential for wind, solar and geothermal resources often do not have the transmission infrastructure in place to get the green power on the grid,” said California ISO Board Chair Mason Willrich. “The ISO proposed and FERC approved a new mechanism that paves the way for easier financing and development of needed renewable power projects. Smaller developers no longer bare the brunt of the upfront costs of investing in the transmission lines. This is a big step in meeting California’s renewable energy goals.”
The Highwind Project, at an estimated cost of $46.1 million, would not ordinarily need board approval as it is under the $50 million threshold. The interim approval process under the LCRI though requires board designation as a renewable area.
A preliminary report from the Renewable Energy Transmission Initiative (RETI) looked at 37 Competitive Renewable Energy Zone (CREZ). The Tehachapi resource area ranked seventh best for economic and fourth best for environmental. The Tehachapi wind resources area was also identified as having the largest potential annual energy output of all evaluated zones, with an estimated 25,091 GWh per year.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus