FortisBC's Okanagan Transmission Reinforcement Project Approved
The British Columbia Utilities Commission (BCUC) has announced its approval for FortisBC's Okanagan Transmission Reinforcement project (OTR) application.
FortisBC anticipates that construction activity for the $141 million project will begin in the spring of 2009 and anticipates project completion in 2011.
"We remain committed to regular communication with local residents and surrounding communities and will make every effort to minimize disruption during construction," added Sam.
In its decision, the BCUC approved plans to upgrade the existing overhead transmission lines from 161kV to 230kV from Vaseux Lake south to Oliver, and Vaseux Lake north to Penticton, and the addition of a 230kV line from Vaseux Lake north to Penticton. The decision also approves the construction of a new electrical substation in Oliver east of the current station, and modifications to the current Oliver substation as well as the Vaseux and RG Anderson substations.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus