ERCOT Board Recommends Approval of ETT Proposed Transmission Line from Laredo into Rio Grande Valley
The Electric Reliability Council of Texas Board of Directors today endorsed and deemed "critical to reliability" a 345-kV transmission project proposed by Electric Transmission Texas LLC from the Laredo area into the Lower Rio Grande Valley. ETT is a joint venture between subsidiaries of American Electric Power and MidAmerican Energy Holdings Company.
ETT's proposed transmission project includes construction of approximately 163 miles of 345-kV transmission lines that will connect ETT's Lobo Substation near Laredo with substations north of Edinburg. The cost of the project is estimated at approximately $300 million. The ERCOT board recommendation also endorsed the need for AEP Texas to reconductor two existing 345-kv lines and upgrade substation facilities at an additional anticipated cost of $225 million.
"The endorsement from the ERCOT board clearly establishes the need for this transmission project and paves the way for a Certificate of Convenience and Necessity (CCN) application from the Public Utility Commission of Texas (PUCT)," said ETT President Calvin Crowder. "Currently, there are only two 345-kV transmission lines serving the Valley. Both of the existing lines import power from the Corpus Christi area and run parallel to the Gulf Coast, which means both are vulnerable to hurricanes and other severe weather. The import capacity of these lines is limited, and the ability to schedule maintenance often can be a problem."
The need for transmission improvements was reinforced during the February rolling outages throughout the state. On the morning of Feb. 2, ERCOT called for firm load to be shed across the grid. The AEP Texas share of the load shed was 380 MW. After the resumption of normal activities, the Valley continued to face the possibility of outages due to severe weather. On the evening of Feb. 3, AEP Texas shed 300 MW of load in the Valley as a result of the loss of a generator and transmission import limitations.
Construction of the line also should further improve transmission reliability in the Laredo area.
ETT anticipates filing a CCN application from the PUCT in 2012 with completion of the project envisioned for 2016. ETT will develop potential routes and conduct environmental studies prior to scheduling open houses to discuss the project with landowners.
ETT acquires, constructs, owns and operates transmission facilities within the ERCOT, primarily in and around the AEP Texas Central Company and AEP Texas North Company service territories.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus
















