Resources

On Demand Media

Demand Viewing

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

White Papers

How NERC CIP and Security Issues Impact Substation Design and Deployment

Read this whitepaper to learn about a variety of security strategies that can be implemented today and how they will enable you to respond to evolving security requirements

Utility Network Design and Data Management:

Autodesk Utility Design and Autodesk Topobase - Combining Autodesk® Utility Design and Autodesk® Topobase(tm) software applications enables utility organizations to harness best-in-class platforms for utility network design and data management.

AutoCAD Map 3D and Autodesk MapGuide Enterprise:

Powerful, Affordable, Open GIS - With open data standards, CAD integration, and a shared API, AutoCAD® Map 3D and Autodesk MapGuide® Enterprise software products streamline workflows and maximize the value of geospatial data seamlessly-from the desktop to the Web.

More White Papers


         Subscribe in NewsGator Online   Subscribe in Bloglines

Nebraska Public Power District Finishes Storm Restoration

At 4:31 p.m. last Friday, the Nebraska Public Power District placed into service the last of 37 transmission line segments damaged, or destroyed, by the late December ice storm. This accomplishment comes six weeks ahead of the original reconstruction schedule.

Along with good weather and an ability to secure agreements with multiple contractors early in the reconstruction process, NPPD also received timely access to materials and resources—all of which helped accelerate completion of the initial work scope. The use of helicopters also helped reduce costs and shorten reconstruction time.

“This (reconstruction effort) was a major undertaking on behalf of NPPD employees, contractors and our public power utility partners,” said NPPD President and CEO Ron Asche. “I am extremely proud of the focus to reconstruct the system as quickly, and efficiently, as possible. Nearly three years of traditional work was completed in under four months.”

To help strengthen electric grid reliability and reduce the risk of such significant damage in the future, NPPD replaced its two pole structures with five pole “storm structures” every six to eight miles. NPPD also replaced some pole structures with custom-made laminated poles, designed to bend, but not break. In addition, the telecommunication lines that NPPD lost in several areas due to the initial storm were buried to eliminate future outages.

Several of NPPD’s hired contractor groups, who work on high-voltage transmission line projects across the United States, commented they had never seen one storm cause one utility such extensive transmission system damage. Utility personnel also said it was the worst storm in public power’s history.

"Rebuilding an electrical system that was essentially sliced in half has been a priority for our transmission staff, and we thank our customers for their patience as we rebuilt the system," said Asche. “With this work complete, our transmission priorities will transition to other critical projects such as the conversion and construction of a new 345-kV transmission line from Norfolk to Lincoln, reliability refurbishments at various locations throughout the state, and the pursuit of transmission studies necessary to incorporating more wind generation into our system."

NPPD also plans to continue working with property owners who incurred damage primarily to farm fields and pastures due to construction traffic during reconstruction. The District also has some line re-sagging work to finish, which is estimated to be complete by the first week in June.

At the height of the storm, NPPD and its public power utility wholesale customers lost service to more than 40,000 customers, primarily in Central Nebraska. Service was restored to all customers by Jan. 19, 2007. NPPD sustained damage to 18 substations and a total of 37 transmission line segments totaling 1053 miles. A total of 1137 of NPPD’s transmission line structures were damaged as well as 301 miles of transmission line conductor (wire). Between 200 and 300 contract workers assisted in the reconstruction effort.

While costs continue to be finalized, total expenses for restoration and reconstruction currently stand at $123.7 million. Approximately $74 million of this amount is expected to be reimbursed by the Federal Emergency Management Agency. The remaining amount will be financed through long-term debt and paid over 20 to 25 years.

NPPD sustained another $34 million in storm-related expenses due to the need to pay for replacement energy costs as a result of transmission line damage restricting the amount of generation capacity received from Gerald Gentleman Station. This amount does not qualify for any federal disaster payments. NPPD is using $22 million of existing District funds in a Rate Stabilization Account to partially off-set the $34 million in increased energy costs. The remaining balance of $12 million is being recovered over a 12-month period through a Production Cost Adjustment charge.

Want to use this article? Click here for options!
© 2008 Penton Media Inc.

Most Read

Community

Blog

Gene Wolf

IEEE Blog

IEEE PES
Gene Wolf

Thousands of attendees and exhibitors are poised to take part in the biggest event of the electric utility industry, the 2008 IEEE PES Transmission and Distribution Conference and Exposition hosted by ComEd in Chicago. The IEEE Blog is a unique tour of the 2008 PES Expo, updated regularly by Gene Wolf, chairman of the IEEE PES T&D Committee.

Read More

Webcasts

Supercondutor Cable Systems

Sponsored by American Superconductor

Transmission & Distribution World presents Superconductor Cable Systems, A Part of the Increasing Bulk Power Transfer Series.

Register Now!


Evolution of Next Generation Wireless Communications in Power Delivery

Sponsored by Alcatel-Lucent

Evolution of Next Generation Wireless Communications in Power Delivery - seeing wireless communications solutions emerge to enable more efficient operations.

Register Now!


Gain insight into Oracle's entry into the Utility Applications market place

Sponsored by Oracle

This session is a peak into how Oracle is executing the strategy one year later. A key aspect of this transition is how a customer project, like Hawaiian Electric made it through the transition.

Register Now!

More Webcasts

Featured Activity

SEE Annual Conference & Trade Show

The Southeastern Electric Exchange celebrates its 75th Anniversary at the PROUD PAST, BRIGHT FUTURE 2008 Conference in New Orleans, June 25-27. The theme uniquely reflects SEE’s history: helping utility members come together to create a culture of professional development, growth, learning, and commitment to quality.

Jobzone
  • June Issue
  • May Issue
  • April Issue
  • March Issue
  • February Issue
  • January Issue
  • December Issue

Browse Back Issues