Phase I of Nebraska Transmission Line Project Complete
With the energizing of Shell Creek Substation north of Columbus on June 13, Phase I of Nebraska Public Power District’s new transmission line project to increase reliability in east-central Nebraska is essentially complete.
"Energizing Shell Creek Substation is an important milestone in NPPD’s Electric Transmission Reliability Project," said Project Manager Craig Holthe. “Completion of Phase I will ensure the reliable delivery of electric energy to Nebraska homes, farms, businesses and industry during peak demands this summer.”
Three main components composed Phase I: 1) expansion of Hoskins Substation near Norfolk, and; 2) construction of Shell Creek Substation [both 1 and 2 include installation of new, high-voltage transformers]; and 3) upgrade the voltage capacity of approximately 40 miles of existing high-voltage transmission line between Hoskins Substation and Shell Creek Substation. Phase I was budgeted at approximately $20 million.
Phase II of the ETR-Project calls for expansion of Columbus East Substation and construction of approximately 80 miles of 345 kV high-voltage transmission line between Shell Creek Substation and Lincoln Electric System's Northwest 68th and Holdrege Substation, near Lincoln.
Following a nearly year-long public involvement and line route selection process, Phase II is currently engaged in engineering, surveying and right-of-way acquisition activities. Actual construction of the new line is scheduled to begin this fall at locations where right-of-way easements have been acquired.
In other project-related news, on June 24 the Nebraska Public Service Commission (NPSC) approved the new line portion of the ETR-Project. The NPSC determined that the new transmission line conforms to the National Electrical Safety Code, the laws of the State of Nebraska, and the rules and regulations of the Commission.
Want to use this article? Click here for options!
© 2008 Penton Media Inc.












