CL&P Announces Completion of 345-kV Line Upgrade
Connecticut Light & Power Co. (CL&P; Hartford, Connecticut, U.S.), a Northeast Utilities subsidiary, has completed approximately 8.6 miles (13.8 km) of the overhead portion of 345-kV electric transmission line from Bethel to Norwalk in southwestern Connecticut. The line was placed in service in October 2006.
CL&P contracted InfraSource Services Inc. (Media, Pennsylvania, U.S.), a specialty contractor servicing utility transmission and distribution infrastructure in the United States, to construct the lines through its business units M. J. Electric and InfraSource Transmission Services.
The project entailed new 345-kV and reconstructed 115-kV transmission line installations, including surveying, right-of-way clearing/access, road construction, foundation installation and removals. InfraSource installed 8.6 miles of a new 345-kV transmission line, a combination of laminated wood H-frames (26 structures) and steel monopoles (58 structures) with new bundled conductor throughout, and removed a portion of the existing 115-kV line, which was replaced with an underground cable system.
InfraSource worked side by side with CL&P on a portion of the work where the existing 115-kV line was replaced with a 115-kV/345-kV composite line for about 1.3 miles (2 km).
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus