Resources

On Demand Media

Demand Viewing

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

White Papers

Designing Energy Services for Commercial and Industrial Customers

Over the past year, technology advances and high energy prices have stimulated interest in Advanced Metering Infrastructure (AMI). Discussions are wide-ranging. Some focus globally: Australian and Canadian “smart metering”, new European Union requirements, the results of time-of-use pilots that arose in the wake of California’s deregulation debacle.

More White Papers

Marketplace Ads

  • Trip Wire

    Automate NERC Cyber Security Compliance

  • Ike Blog

    Reports From The Front

Case Studies

York Region Finishes Tasks Faster

We all know that data integration improves productivity and York Region is living proof. Using AutoCAD® Map 3D, York saved time and money by relying on its AutoCAD-trained staff to quickly implement a new system that incorporates both CAD and GIS.

Save Time with CAD and GIS Integration

Read how the Public Works Department of the City of Tacoma (Tacoma), Washington, uses its geospatial data to do everything from issuing building permits and managing waste water to maintaining streetlights

Six-Wire Solution

When American Electric Power decided in 1991 that its proposed 765-kV transmission line from West Virginia to Virginia would include the first six-wire bundles in North America, almost 50 years of engineering advances — rarely accomplished easily — were behind the decision. Following are some of AEP's transmission advances.

1946 AEP's first extra-high-voltage (EHV) lab construction was started adjacent to the Tidd Plant near Steubenville, Ohio. AEP's highest voltage transmission lines operated at 138 kV at the time. Tidd lab voltages could be varied between 265 kV and an unheard of 532 kV. Higher-capacity lines were needed to accommodate the larger output of generating units, 150 MW during the 1940s.
1950 AEP concluded that 330 kV (later increased to 345 kV) was the optimal transmission voltage.
1953 The first 345-kV line went into service. Problems with audible noise and radio interference caused operating voltage reduction to the familiar 138 kV. Measures implemented included: strict conductor-handling guidelines being adopted and conductor size increased from a 1.6-inch to 1.75-inch (40.6-mm to 44.4-mm) diameter. Performance improved greatly after several years of weathering.
1958 The first section of bundled two-wire 345-kV lines went into service. Previously, all 345-kV lines had a single wire per phase. AEP built a total of about 3800 circuit miles (4830 km) of 345-kV lines.
1960 A larger transmission test lab at Apple Grove, West Virginia, replaced the Tidd operation. A five-year program was started to test voltages up to 775 kV and combinations of four-wire bundles.
1966 Based on this R&D and the need to accommodate 800-MW units, AEP announced it would build a new network — 1050 circuit miles (1658 km) in five states — of 765-kV transmission lines to overlay its existing grid. (The previous November, Hydro-Québec announced plans to build the world's first 735-kV line, which became Canada's Manic-Boucherville line, completed three years later.)
1969 Problems arose with corona-caused noise in wet conditions, especially at higher elevations. As a stopgap, new lines were operated at lower voltage while the conductors aged. The original 765-kV phase bundle consisted of four 1.165-inch (30-mm)-diameter Rail (954-kcmil ACSR) wires arranged in a square with sides of 18 inches (457 mm).
1972 AEP's originally proposed 1050-mile 765-kV system was essentially completed. The advent of 1300-MW generating units called for additional 765-kV lines.
1974 Subsequent 765-kV system expansion used larger 1.385-inch (35 mm) Dipper (1351.5-kcmil ACSR) conductors. This reduced noise and line losses.
1968 to 1987
These early 765-kV operational problems spawned five generations of mobile laboratories. Increasingly sophisticated data-gathering vans measured and recorded both corona and electromagnetic phenomena throughout the system.
1985 Completion of 20th century additions to AEP's 765-kV system: 24 years from planning to completion, 2022 miles (3254 km), 5300 steel towers, 2200 aluminum towers, 24,500 miles (39,429 km) of conductor and 2.5 million ceramic insulators.
1990 The need to reinforce the bulk transmission delivery system in southern West Virginia and southwest Virginia led to AEP's proposal to extend its 765-kV system from its Wyoming Station (Oceana, West Virginia) 110 miles (177 km) to its Cloverdale Station (Roanoke, Virginia).
1998 During regulatory proceedings in Virginia, however, the line's destination was changed to Jacksons Ferry Station. The West Virginia Public Service Commission approved the project.
2001 The Virginia State Corporation Commission issued its final order approving the project.
2002 The lead federal agency, the U.S. Forest Service, granted approval to construct the line.
2003 to 2004
Right-of-way clearing began in December 2003; tower foundation construction started in April 2004; and, the first tower was erected in August 2004.
2006 AEP's Wyoming-Jacksons Ferry 765-kV line was energized in June 2006, the first such line in North America with six-wire bundles.
Chronology supplied by AEP

Elevation Operation voltage on 765-kV base
(ft) (m) 1.0 p.u. (dBA) 1.02 p.u. (dBA) 1.04 p.u. (dBA)
800 244 49.0 50.0 51.0
2500 762 50.7 51.7 52.7
3800 1159 52.0 53.0 54.0

Approximate foul-weather mean audible noise levels at the edge of a 200-ft (61-m)-wide right-of-way. (Note: Table shows noise levels as a function of elevation and operation voltages for 765-kV line using 6-Tern design.)

Bundle diameter for 6-Tern Audible noise reduction below 4-Dipper at 25.5-inch (648-mm) bundle diameter
(inches) (mm) (dBA)
25.5 648 4.6
28 711 4.9
30 762 5.1

Audible noise reduction of various 6-Tern bundle diameters, compared with 4-Dipper at a 25.5-inch diameter.

GETTING A SIX-WIRE TENSIONER

You want to string and tension a six-wire bundle on your latest transmission line project. The device that does this is a tensioner. So you go to your local transmission line building supply store and find the tensioner aisle. There are single-, dual-, triple- and quad-conductor tensioners. But, the six-conductor version seems to be out of stock. No, a stock check reveals the store never ever had them. It's a special order item.

PAR Electrical Contractors (Kansas City, Missouri, U.S.), a division of Quanta Services, was in such a situation when it contacted Lloyd Morgan at Morpac Industries Inc. (Vancouver, Canada) regarding a six-conductor bundle tensioner for AEP's new 765-kV line. The good end to this story is that PAR ordered two machines, and Morgan designed, built and delivered the first unit in 120 days. But, there is, of course, more to the story.

THE SOURCE

Born in 1918 and still working every day, Lloyd Morgan started as a line contractor in 1956 and subsequently began developing his own line of high-quality line-stringing equipment. Early field experience led Morgan to an important realization: smaller line crews outfitted with the best tools and equipment resulted in safer, more cost-effective and productive line-stringing operations. Founded as Morgan Power Apparatus, and currently doing business as Morpac Industries Inc., the Morgan name has always been associated with state-of-the-art stringing equipment known for exceptional quality and ruggedness.

Morpac has built many tensioners over the decades ranging from one-wire to four-wire configurations, most of which are built to customers' specifications. Never having built a six-wire tensioner, this new design was loosely based on a tensioner that can be configured in several combinations of bullwheel sizes and bundle numbers. But, this machine required mostly custom parts to fit all six pairs of bullwheels and their associated hardware.

THE TENSIONER

As with all Morgan equipment, this tensioner is equipped with both innovative and decades-old, time-tested features. Half of the bullwheels on the tensioner are tilted to allow the conductor to advance to the next groove on the straight bullwheels without having side load on the wire. The side load often generates a twisting force in the wire, which can eventually lead to failure of the pulling line or conductor if not dealt with properly.

The tensioner is also equipped with an ecologically friendly Cummins 130-hp engine. It is run during tensioning as a giant flywheel to eliminate wire oscillations during the stringing operation. It also allows the tensioners to be used for sagging up to 20,000 lbs per wire.

Providing the tensioning force to Morpac's tensioners is a huge water-cooled brake manufactured by Eaton (Cleveland, Ohio). The coolant runs through a gigantic twin-core radiator capable of expelling up to 540 hp worth of heat in the harshest conditions. This brake has a fine and coarse adjustment and each conductor is individually controlled via its own clutch.

Each drive bullwheel has its own expanding-bladder clutch, which allows it to be operated independently for operations such as sagging, leveling the running board while tensioning or steering the running board through angle towers. This clutch, measuring 20.25 inches (51 cm) in diameter and 7 inches (17 cm) wide, was originally developed by B.F. Goodrich for the U.S. Air Force as aircraft wheel brakes, but is now manufactured in-house. Morpac has been using this device as a clutch and brake on reel stands successfully for decades, and has found that the 445 sq inches (2871 sq cm) of braking surface area provides exceptionally smooth conductor payout.

These features are common among many of Morpac's machines and are why many of its machines are still in use after more than 40 years of service. Morpac Industries has, in the decades it's been in business, branched out into other markets, but its core business and the bailiwick of founder has always been high-quality line-stringing equipment.


Commenting terms of use

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.

General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.

blog comments powered by Disqus

Want to use this article? Click here for options!
© 2008 Penton Media Inc.

Most Read

Community

Hurricane Ike Coverage

Hurricane Ike Coverage
On September 12th, Hurricane Ike tore through the Gulf Coast, wreaking havoc on lives and property. Transmission & Distribution World’s Rick Bush is headed to the region to provide a first-hand account of the damage including an insider view of utility emergency-response efforts. His reports and subsequent feature coverage will highlight how utilities, contractors and suppliers work as a team to restore power as quickly as possible.
Read Rick’s Blog, Ike: Reports from the Front

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

Webcasts

ACSS and HS285 Extend Grid Capacity

Sponsored by Southwire

There are capacity bottleneck situations, where new overhead transmission line construction is not a practical reality. In some of these situations overhead lines are in place and they are not able to provide the transfer capacity needed.

Register Now!


Supercondutor Cable Systems

Sponsored by American Superconductor

Transmission & Distribution World presents Superconductor Cable Systems, A Part of the Increasing Bulk Power Transfer Series.

Register Now!


Evolution of Next Generation Wireless Communications in Power Delivery

Sponsored by Alcatel-Lucent

Evolution of Next Generation Wireless Communications in Power Delivery - seeing wireless communications solutions emerge to enable more efficient operations.

Register Now!

More Webcasts

Featured Activity

T&D World University 2008

Get expanded education, practical experience and unprecedented networking in 3 days at T&D World University, the Continuing Education Program for Utility Management, Engineers and Technical Professionals. October 27-29, 2008, Dallas, TX. With CEU-Earning Seminars, Specialized Tracks, 59+ Courses, T&D allows you to maximize your time, with minimal work interruptions. Bring your team to this productive learning environment.

Jobzone
  • November 2008 Issue
  • October 2008 Issue
  • September 2008 Issue
  • August 2008 Issue
  • July 2008 Issue
  • June 2008 Issue
  • May 2008 Issue

Browse Back Issues