Resources

Search, compare, and request quotes for nearly 13,000 products with detailed listings:

Blogs

  • 2012 IEEE PES Show Blog

    The IEEE Blog is a unique tour of the 2012 PES Expo in Orlando, FL, by Gene Wolf, former chairman of the IEEE PES T&D Committee.

White Papers

» More White Papers

Follow Power Editor Nikki Chandler on

Follow Technology Editor on Vito Longo

Find T&D World on Facebook

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

  
   

Progress Energy Carolinas Plans Plant Addition, New Transmission Line

As population and energy usage in southern and eastern North Carolina continue to grow, Progress Energy Carolinas plans to invest an estimated $700 million to $750 million in building new electric generation capability at its energy complex in Richmond County and new transmission capacity to move electricity to where it's needed.

Progress Energy's continuous assessment of electric system requirements identified the need for the project to be in service by mid-2011, to help ensure a continued reliable supply of electric service to homes and businesses.

Ensuring state-of-the-art power plants and delivery systems is a critical part of Progress Energy's balanced solution for meeting the needs of a service area growing by 25,000 to 30,000 households and businesses each year. The company also is focused on significantly increasing energy efficiency (through a variety of customer programs under way or in development) and on responsible investments in renewable energy technologies.

The new power unit - an approximately 570-MW combined-cycle plant fueled primarily by natural gas - is planned for the company's existing Richmond County Energy Complex south of Hamlet. The complex is the company's third largest in the Carolinas, with more than 1,230 MW of existing gas-fueled electric generation. No additional property offsite is needed to accommodate the power plant addition.

To ensure that the power produced at the new plant moves efficiently and reliably to where it is needed to meet growing customer demand, Progress Energy also plans a new 230-kV transmission line of approximately 64 miles between electric substations in Richmond County and Cumberland County. The easternmost portion of the line will be on the property of Fort Bragg Army Base.

The new transmission line will begin at Progress Energy's Richmond County Energy Complex switchyard, south of Hamlet, and end at a substation on Woodruff Street on Fort Bragg Army Base.

Progress Energy expects to complete the plant and transmission line construction by June 1, 2011. Transmission line route selection, easement acquisition, additional engineering and design and other milestones will occur before construction gets under way. The project will require approval by the N.C. Utilities Commission and other agencies, as well as the Progress Energy board of directors.

The in-service date is based on current information. In-service dates for projects of this sort sometimes move based on changes in growth and usage projections and other criteria. The total length of the new transmission line will depend on the final route selected.

Progress Energy has sent letters to residents whose property might be affected directly by any of the potential power line routes.

A final route for the transmission line will be chosen in the first quarter of 2008, and Progress Energy expects to base that selection in large part on public input as well as input from state and federal agencies with an interest in the project. Acquisition of the transmission line easements begins in mid-2008 and is scheduled to continue until mid-2009. Clearing for the line will begin in mid-2009. Construction is scheduled to begin in early 2010 and to be completed by mid-2011. Plant construction is scheduled to begin in 2009 and be completed in 2011.

The new transmission line will be built on 100-foot-wide property easements. Progress Energy will be investigating a number of routing options to determine the route that poses the least overall impact (to property owners, the environment, cultural and natural resources, etc.). Current construction plans call for the line to be suspended on steel-pole structures (some with guy wires and some without). The poles are generally 80 to 110 feet above ground and spaced every 500 to 700 feet apart, depending on terrain. Easements enable Progress Energy to build and maintain the line. Property owners retain ownership of the land, with some restrictions on its use.

The project is one of several major transmission system enhancements planned or under way throughout Progress Energy's service area as part of the company's plan to ensure a continuous, reliable flow of electricity to customers. Building and maintaining state-of-the-art power plants and delivery systems is a key component of a balanced solution to meeting future energy needs - along with increased energy efficiency and investments in renewable energy technologies.

Want to use this article? Click here for options!
© 2012 Penton Media Inc.


Acceptable Use Policy

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.

General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.

blog comments powered by Disqus

T&D TV

Most Read


Find Other Popular Items

Features

Vegetation Management
Grid Optimization

Upcoming Webcasts

Transmission & Distribution World allows you to access live and on-demand webcasts. Webcasts are available during their scheduled date and time. If you are unable to attend at the scheduled time, these free events will be available On-Demand for viewing at your convenience.


On-Demand Webcasts

» View More Webcasts

Jobzone
  • Transmission & Distribution World May 2012 Issue
  • Transmission & Distribution World April2012 Issue
  • Transmission & Distribution World March 2012 Issue
  • Transmission & Distribution World February 2012 Issue
  • January 2012 Issue
  • December 2011 Issue
  • November 2011 Issue

Browse Back Issues