Resources

On Demand Media

Demand Viewing

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

White Papers

Moving Toward Utility-Scale Deployment of Dynamic Pricing in Mass Markets

Prior studies have shown that dynamic pricing can provide numerous benefits to utilities and customers alike.

A Deployment Strategy for the Smart Grid: From the Generator to the Refrigerator

This white paper describes a coordinated, prioritized and customer-based development strategy for utilities considering the Smart Grid initiative.

A Guide to Transformer Winding Resistance Measurements

Matz Ohlen and Peter Werelius of Megger discuss the unique method of winding resistance measurements in transformers and how they are a fundamental importance to detecting potential mechanical and electrical problems that other methods are unable to detect the field.

Smart Metering for Water Utilities

Should water utilities replace current consumption meters with “smart metering” systems that provide more information to both utilities and customers? This question is being hotly debated in today’s electric utility industry but currently appears to be of less interest in the water industry.

Gene Kim's Practical Steps to Achieve and Maintain NERC Compliance

Gene Kim, CTO of Tripwire, describes seven practical steps owners and operators of the bulk power system can take to meet the mandatory NERC-CIP standards, helping them avoid huge fines for non-compliance and protect North America’s bulk power system.

More White Papers

Marketplace

Trip Wire

Automate NERC Cyber Security Compliance

Reports from Spain Blog

Electric Solar: Reports from Spain


         Subscribe in NewsGator Online   Subscribe in Bloglines  

PSE&G Endorses New Transmission Lines To Improve Long-term Electric Reliability in New Jersey

Public Service Electric and Gas Company (PSE&G) has endorsed construction of several new 500-kV transmission lines that will significantly improve the long-term reliability of the electric system that serves New Jersey customers.

The utility supports construction of three additional 500-kV lines to reinforce transmission facilities on existing rights of way:

  • An 80-mile line from Camden County (New Freedom) north to Middlesex  County (Deans) 
  • A 30-mile line from Somerset County (Branchburg) to Essex County  (Roseland) 
  • A 135-mile line from Luzerne County, PA to Essex County (Roseland).

"These new transmission lines are essential for New Jersey to meet the growing demand for electricity over the long term," said Ralph LaRossa, president and chief operating officer of PSE&G. "PJM Interconnection, the regional transmission organization, has already identified a number of areas in which additional transmission facilities are needed to ensure the continued reliability of our region's electric grid and our state's economic growth. While long-term reliability is driving the need to build these lines, we also expect that they will eventually ease transmission congestion and lower electric prices for our customers."

In April, the U.S. Department of Energy designated New Jersey and surrounding areas as critical congestion areas, highlighting the need for transmission investment.

LaRossa noted that these reinforcements, which would follow existing transmission pathways, are needed in addition to initiatives already under way to reduce electric use by boosting energy efficiency and renewable energy sources. For example, PSE&G recently announced plans to provide long-term financing of solar systems, as well as convert a portion of its vehicle fleet to hybrids.

New Freedom to Deans line

The new 500-kV south-north line would originate at PSE&G's New Freedom station in Winslow Township, and travel northeast to connect with PSE&G's Deans station in South Brunswick, parallel to an existing 500-kV line. The proposed circuit would run on existing rights of way and parallel to existing transmission facilities where feasible, thereby minimizing disruption to New Jersey municipalities as well as the impact on the environment. The exact route of the new line would be determined once the proposal is accepted by PJM, which is responsible for planning and operating the regional transmission system in 13 states and the District of Columbia.

This line will be discussed with PJM as one solution to move additional electricity from the southern to the central part of New Jersey. In examining several potential routes, PSE&G will work with PJM and other transmission owners to determine the best location. If PJM agrees that the project is preferred to other alternatives, the line would become part of PJM's Regional Transmission Expansion Plan, subject to approval by the organization's board of managers.

Branchburg to Roseland line

The second line would run from PSE&G's Branchburg station in Somerset County to the Roseland station in Essex County. This reinforcement would use the same right of way as an existing circuit that carries lower voltages. If this route is selected and approved by PJM, this route would also become part of the Regional Transmission Expansion Plan.

Susquehanna to Roseland line

Later this month, PJM is expected to approve a third project to build a 500-kilovolt line that would run west to east from Susquehanna station in Salem Township, Pennsylvania, to PSE&G's Roseland, New Jersey, station. The project would also include construction of a new switching station on utility-owned property in Morris County, and would involve another utility.

Although these new lines are still in the planning stages, PSE&G expects its portion of the cost to be about $1 billion, which would be shared by all customers in the PJM territory. The utility's 2.1 million electric customers would pay about 7.5 percent of the costs under transmission rates approved by the Federal Energy Regulatory Commission (FERC). If selected and approved by PJM, these lines would be built over five to eight years.

Want to use this article? Click here for options!
© 2009 Penton Media Inc.


Acceptable Use Policy

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.

General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.

blog comments powered by Disqus

Most Read

Community

Connecting Solar to the Grid

Electric Solar: Reports from Spain
Rick is joining a U.S. contingent traveling with the Solar Electric Power Association to tour large-scale grid connected solar installations in Southern Spain. Check out Rick’s daily blog and experience the world of solar that is in the here and now.
Read Rick’s Blog, Electric Solar: Reports from Spain

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

Webcasts

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

ACSS and HS285 Extend Grid Capacity

Sponsored by Southwire

There are capacity bottleneck situations, where new overhead transmission line construction is not a practical reality. In some of these situations overhead lines are in place and they are not able to provide the transfer capacity needed.

Register Now!


Supercondutor Cable Systems

Sponsored by American Superconductor

Transmission & Distribution World presents Superconductor Cable Systems, A Part of the Increasing Bulk Power Transfer Series.

Register Now!

More Webcasts

Jobzone
  • June 2009 Issue
  • May 2009 Issue
  • April 2009 Issue
  • March 2009 Issue
  • February 2009 Issue
  • January 2009 Issue
  • December 2008 Issue

Browse Back Issues