Resources

On Demand Media

Demand Viewing

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

White Papers

Moving Toward Utility-Scale Deployment of Dynamic Pricing in Mass Markets

Prior studies have shown that dynamic pricing can provide numerous benefits to utilities and customers alike.

A Deployment Strategy for the Smart Grid: From the Generator to the Refrigerator

This white paper describes a coordinated, prioritized and customer-based development strategy for utilities considering the Smart Grid initiative.

A Guide to Transformer Winding Resistance Measurements

Matz Ohlen and Peter Werelius of Megger discuss the unique method of winding resistance measurements in transformers and how they are a fundamental importance to detecting potential mechanical and electrical problems that other methods are unable to detect the field.

Smart Metering for Water Utilities

Should water utilities replace current consumption meters with “smart metering” systems that provide more information to both utilities and customers? This question is being hotly debated in today’s electric utility industry but currently appears to be of less interest in the water industry.

Gene Kim's Practical Steps to Achieve and Maintain NERC Compliance

Gene Kim, CTO of Tripwire, describes seven practical steps owners and operators of the bulk power system can take to meet the mandatory NERC-CIP standards, helping them avoid huge fines for non-compliance and protect North America’s bulk power system.

More White Papers

Marketplace

Trip Wire

Automate NERC Cyber Security Compliance

Reports from Spain Blog

Electric Solar: Reports from Spain


         Subscribe in NewsGator Online   Subscribe in Bloglines  

Puget Sound Energy Investing Heavily in Electric Infrastructure

Puget Sound Energy in Washington state is investing approximately $421 million in service-area infrastructure improvements in 2008, of which about $247 million is earmarked for capacity and reliability upgrades, and about $174 million is allocated to meet growing customer needs (for electric and gas).

“It takes a lot of planning and coordination to do this amount of work in a year,” said Bert Valdman, executive vice president and chief operating officer for PSE. “We are proud of the work being done by PSE employees and contractors as we make the necessary investments in our electric and natural gas systems to ensure our customers throughout our service area have safe, reliable service now and in the future. We also thank the communities and our customers for their patience and support as we do this work on their behalf.”

PSE’s 2008 electric system investments include:

  • Building four miles of new 230 kV transmission line and five miles of new 115 kV transmission line.
  • Re-conductoring (replacing old power lines with new power lines) 54 miles of PSE’s transmission system.
  • Replacing or remediating (injecting with silicone to extend the life of cable) approximately 70 miles of underground cable.
  • Replacing 800 poles.
  • Constructing six new distribution substations – two in Whatcom County and one each in Island, King, Jefferson, and Thurston counties.
  • Upgrading seven distribution substations and six transmission systems in Whatcom, Skagit, Snohomish, King, Kitsap, and Thurston counties.

PSE 2008 major projects in the counties served by the utility include:

Island County

  • Island County reliability project – Implementing a multi-year vegetation management project to improve PSE’s system reliability on Whidbey Island and reduce tree-related outages at an estimated cost of $1 million. Anticipated phase-one completion: winter 2008.
  • Useless Bay substation – Building a new substation to improve reliability to the south end of Whidbey Island at an estimated cost of $10 million to $12 million. Anticipated completion: fall 2010.

Jefferson County

  • Chimacum substation – Completed the construction of a new $5 million substation in May 2008 to improve service reliability for customers in the Port Hadlock area of Jefferson County.

King County

  • Bellevue Braids-Lake Hills Connector – Installing a new natural gas pipeline in downtown Bellevue at an estimated cost of $13.3 million to provide uninterrupted service to existing customers and accommodate projected demand. Anticipated completion: winter 2008.
  • Covington-Berrydale 230 kV – Building a new transmission line at an estimated cost of $12.6 million to improve reliability and meet growth needs in the Covington area. Anticipated completion: fall 2008.
  • Factoria substation – Rebuilding the Factoria substation at an estimated $6.5 million cost to reduce outages and enhance capacity in Bellevue. Anticipated completion: spring 2009.
  • Four Corners substation – Building a new electric distribution substation at an estimated cost of $5.5 million to meet increased demand for electricity in the Maple Valley area. Anticipated schedule: begin construction spring 2009.
  • Juanita substation – Doubling the size of the existing substation at an estimated cost of $4.2 million to increase reliability and meet growing demand for power in the Juanita, Totem Lake and Kingsgate areas of Kirkland. Anticipated schedule: begin construction in spring 2009.
  • Kent-Black Diamond natural gas line – Upgrading the Kent/Auburn natural gas system at an estimated cost of $5.25 million to reinforce the existing system currently serving Kent, Auburn, Federal Way, and Vashon Island. Anticipated schedule: begin construction fall - winter 2008.
  • Lake Hills-Phantom Lake transmission line – Building a new transmission line to connect the utility’s existing Phantom Lake and Lake Hills substations at an estimated cost of $3.5 million to increase electric system reliability and capacity. Anticipated schedule: begin construction fall 2009.
  • Novelty substation and electric transmission line – Building a new transmission line between Northeast Novelty Hill Road and Avondale Road Northeast on PSE’s existing transmission line corridor at an estimated cost of $8.4 million to increase reliability and meet additional demand resulting from ongoing growth in Redmond and east King County. Anticipated completion: spring 2009.
  • Talbot Beverly – Replacing aging power poles and installing a new fiber-optic line along 35 miles of transmission line corridor between the Talbot substation in Renton and Snohomish County Public Utility District’s Beverly Park substation in Everett at an estimated cost of $3 million to improve system reliability. Anticipated schedule: construction fall 2008.

Kitsap County

  • Bremerton substation – Demolishing the existing substation and rebuilding and upgrading the facility at an estimated cost of $9 million to increase capacity and reliability as well as help reduce future power outages. Anticipated completion: summer 2009.

Lewis County

  • Chehalis natural gas line – Upgrading approximately 12,000 feet of 4-inch line with 12-inch line at an estimated cost of $4.5 million. Anticipated schedule: construction summer 2009.

Pierce County

  • Frederickson natural gas line – Installing 5.25 miles of 16-inch natural gas line from PSE’s existing Frederickson natural gas station and Clover limit station at 128th Street East and Waller Road at an estimated cost of $14 million to upgrade the utility’s natural gas system in south Tacoma. Anticipated schedule: construction and project completion fall 2008.

Skagit County

  • Fredonia 115 kV line loop – Installing a new .4 mile transmission line at an estimated cost of $1.5 million to $2 million between the Olympic Bay View and Fredonia substations to increase reliability in Skagit County. Anticipated completion: fall 2008.
  • Sedro-Woolley to Beaver Lake new 115 kV and fiber optic line, 230 kV upgrade – Upgrading capacity, including adding a new fiber-optic line, to 4.8 miles of an existing 115 kV transmission line at an estimated cost of $40 million. Anticipated completion: fall 2008.
  • Sedro-Woolley to Horse Ranch rebuild of existing 115 kV line to 230 kV line – Rebuilding 40 miles at an estimated cost of $30 million to $50 million to increase system reliability, help prevent power outages, and support anticipated growth in the area. Anticipated schedule: design 2008-09, construction 2009-10.

Snohomish County

  • Ebey Slough improvement – Replacing aging transmission line structures in Ebey Slough with new poles at an estimated cost of $15 million to protect system safety and reliability. Anticipated completion: fall 2008.

Thurston County

  • North Lacey natural gas line – Upgrading 5.2 miles of 12- and 8-inch natural gas line between Elizabeth Avenue (18th Avenue Southeast) in Olympia and Draham Street Northeast in Lacey at an estimated cost of $11.2 million. Anticipated schedule: construction spring 2009, completion fall 2009.
  • Olympia substation and transmission line conversion – Upgrading the utility’s existing low-voltage 55 kV substations and transmission lines to 115 kV standards in Olympia at an estimated cost of $7.8 million. The 2008-2009 project includes the following work:
-- Saint Clair substation: updating equipment and transmission line terminations. Schedule: completed April 2008.
-- Hawkes Prairie substation: replaced transformer and updated equipment. Schedule: completed May 2008.
-- Luhr Beach substation: removed station equipment and transmission line. Schedule: completed May 2008.
-- Valenica substation: removed station equipment and transmission line. Schedule: completed July 2008.
-- Pleasant Glade substation: installed circuit breakers, updated equipment, modified transmission line terminations. Schedule: completed July 2008.
-- Plum Street substation: demolishing and rebuilding existing substation. Anticipated completion: October 2008.
-- Friendly Grove substation: Constructing a new 115 kV substation adjacent to the existing 55 kV substation, then demolishing the existing substation and modifying existing transmission and distribution lines to accommodate the new station. Anticipated completion: spring 2009. Anticipated conversion completion: winter 2009.

Whatcom County

  • Laurel substation – Building a new substation at an estimated cost of $3.5 million to meet increased demand for electricity in the Cordatta Parkway area in Bellingham. Anticipated completion: fall 2008.
  • Sehome substation – Completed rebuilding the existing substation and upgraded from a 4 kV system to a 12 kV system in March at a cost of $4 million to support long-term capacity and reliability and help reduce future power outages.
  • Semiahmoo substation – Building a new electric distribution substation between Birch Bay and City of Blaine at an estimated cost of $3.9 million to meet increased demand for electricity. Anticipated schedule: begin construction spring 2009, completion fall 2009.

Want to use this article? Click here for options!
© 2009 Penton Media Inc.


Acceptable Use Policy

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.

General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.

blog comments powered by Disqus

Most Read

Community

Connecting Solar to the Grid

Electric Solar: Reports from Spain
Rick is joining a U.S. contingent traveling with the Solar Electric Power Association to tour large-scale grid connected solar installations in Southern Spain. Check out Rick’s daily blog and experience the world of solar that is in the here and now.
Read Rick’s Blog, Electric Solar: Reports from Spain

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

Webcasts

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

ACSS and HS285 Extend Grid Capacity

Sponsored by Southwire

There are capacity bottleneck situations, where new overhead transmission line construction is not a practical reality. In some of these situations overhead lines are in place and they are not able to provide the transfer capacity needed.

Register Now!


Supercondutor Cable Systems

Sponsored by American Superconductor

Transmission & Distribution World presents Superconductor Cable Systems, A Part of the Increasing Bulk Power Transfer Series.

Register Now!

More Webcasts

Jobzone
  • June 2009 Issue
  • May 2009 Issue
  • April 2009 Issue
  • March 2009 Issue
  • February 2009 Issue
  • January 2009 Issue
  • December 2008 Issue

Browse Back Issues