Resources

Search, compare, and request quotes for nearly 13,000 products with detailed listings:

Blogs

  • 2012 IEEE PES Show Blog

    The IEEE Blog is a unique tour of the 2012 PES Expo in Orlando, FL, by Gene Wolf, former chairman of the IEEE PES T&D Committee.

White Papers

» More White Papers

Follow Power Editor Nikki Chandler on

Follow Technology Editor on Vito Longo

Find T&D World on Facebook

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

  
   

Reliability and Growth

The design included one-piece polymer insulators as opposed to a typical series of 18 to 20 porcelain “bells” found on other 345-kV circuits. These insulators and associated hardware assemblies, packaged and supplied by Hubbell Corp., produced a lower initial installed cost and, ultimately, is expected to reduce maintenance costs.

In some cases, the design required custom structures to fulfill special needs. This included single-circuit, single-shaft structures; double-circuit, single-shaft structures with four different voltage levels for the second circuit; double-circuit, single-shaft structures with 46-kV underbuild; two-pole, heavy angle deadend structures; and single- and double-circuit H-frame structures. All steel structures were supplied by Thomas & Betts.

Project designers chose to construct the line using weathering steel poles (with the exception of two galvanized steel poles and one metallized steel pole required by the National Park Service (NPS) at the Namekagon River Crossing) to carry the wires in vertical configurations on single concrete pier foundations. For aesthetics and future maintenance cost savings, ATC specified a weathering finish, which does not require a maintenance cycle like painted poles, on the more than 50 million lbs (22,680 metric tons) of steel used for the single-pole structures.

NAMEKAGON RIVER CROSSING

One of the more complex designs was a double-circuit line section that crossed the Namekagon River, which is the northern tributary of the St. Croix River and is protected by the NPS as a Wild and Scenic Riverway for canoeing and camping. This river crossing is under the jurisdiction of the NPS, which considered several options for the crossing, including both overhead and underground alternatives. The NPS selected an overhead crossing as the preferred alternate mandating that the visual impact of the structures be mitigated by a vegetation screen at the river bank, so the supporting structures would not be easily seen from a canoe in the river. NPS also limited the number of conductors to six instead of the typical 11, in an effort to minimize the line's visibility and to maintain the aesthetic viewscape.

The team used a single-conductor-per-phase design on the 345-kV circuit and removed the two shield wires from three spans — the crossing span and one adjacent span on each side of the river. One of the shield wires was an optical ground wire, so it had to be buried under the river using a directional drill bore to maintain continuity of the fiber signal. The team used surge arresters at the two structures on either side to limit voltages due to lightning strikes or equipment faults, preventing damage to equipment and disruption of service.

To mitigate visual impacts, the NPS required that the crossing span be about 1500 ft (457 m), around double the average span length, and that the structures on either side of the river be less than 125 ft (38 m) tall. To accommodate this, the design team used a special conductor for each of the 345-kV and 161-kV circuits crossing the river. They ordered specialized heavy conductor from Japan, supplied by Sumitomo Cable/J-Power Systems Corp., which was much larger than typical wire and had a rated breaking strength of 200,000 lbs (90,718 kgs) for the 345-kV conductor and 140,000 lbs (63,503 kgs) for the 161-kV conductor. The conductors were deadended to the crossarms to avoid the added height of installing suspension insulator assemblies. All of this required yet another set of special-structure designs, which were handled using custom-designed tubular-steel poles.

ENERGIZED AHEAD OF SCHEDULE

In January 2008, the Arrowhead-Weston line was energized four months ahead of schedule and within the approved budget levels. After 10 years and countless challenges, one of the largest transmission line projects built in the United States in decades was providing a much-needed improvement to the reliability of the regional grid. With the line in place, system operators are able to transfer additional power from western markets through Minnesota into Wisconsin.

The design for this major project was no small feat. The line spans two states, eight counties and 44 towns. At a cost of $435 million, the line can carry 800 MW, providing enough electricity to power 250,000 homes. Although there were many factors to the project's success, much of it can be attributed to the flexibility allowed by the decision to construct the line using single-pole steel structures.

It was also successful because the team was able to adjust to change. When the team unexpectedly hit karst rock while drilling the foundations early in the project, the need for a fast yet durable solution was apparent. The design team was undeterred. They quickly devised a foundation that consisted of four drilled piers tied together with a pile cap and secured to the rock via post-tensioned rods. The on-the-fly design was the epitome of ingenuity and representative of the team's attitude throughout the project: Expect the unexpected.

Pete Holtz is a general manager at American Transmission Co. He has managed several projects in his tenure at ATC since its formation in 2001. Since 2002, he has been the overall manager of the Arrowhead-Weston transmission project. Prior to joining ATC, he spent 26 years at WE Energies managing customer service activities. He holds a bachelor's degree in business administration from the University of Wisconsin-Madison. pholtz@atcllc.com

Ron Gullicks is a supervising engineer at Minnesota Power with 29 years of experience in the design and construction of electric generation, substation and transmission line facilities. Gullicks is a registered professional engineer in Minnesota, Wisconsin and North Dakota. He holds a bachelor's degree in civil engineering and a master's degree in sanitary engineering from the University of North Dakota. rgullicks@mnpower.com

Dave Valine is an operations manager for Minnesota Energy, a subsidiary of Integrys Energy Group and a sister company to Wisconsin Public Service. In his 19 years at Wisconsin Public Service, Valine worked primarily in transmission licensing, engineering and construction. He holds bachelor's degrees in mining engineering and electrical engineering from Michigan Tech University and is a registered professional engineer in Wisconsin. dlvaline@minnesotaenergyresources.com

David W. Wedell is a senior project manager at POWER Engineers. He has more than 30 years of experience in the design of high-voltage and extra-high-voltage transmission lines. He has managed transmission line design projects in the United States, Saudi Arabia and Thailand. Wedell holds a bachelor's degree in civil engineering from Southern Illinois University. dwedell@powereng.com

Comparison of 345-kV conductors used on Arrowhead-Weston project.
Northern 20 miles Remainder of line (excluding Namekagon River Crossing) Namekagon River Crossing
Voltage 345 kV 345 kV 345 kV
Conductor 1272 kcmil 954 kcmil JP-KTACSR
45/7 ACSR-Bittern 54/7 ACSR-Cardinal UGS-1360
Two per phase Two per phase One per phase
Diameter 2 × 1.345 inches 2 × 1.196 inches 2.114 inches
Weight 2 × 1.434 = 2.868 lbs/ft 2 × 1.229 = 2.458 lbs/ft 4.4 lbs/ft
Rated breaking strength 2 × 34,100 = 68,200 lbs 2 × 33,800 = 67,600 lbs 200,077 lbs
Max. design tension 2 × 24,000 = 48,000 lbs/phase 2 × 14,500 = 29,000 lbs/phase 64,200 lbs
Conductor temperature
At 2770 A 212°F 212°F 222.6°F
Max. continuous 212°F 212°F 302°F
*All conductor ratings based on 90°F ambient; wind speed 4.4 ft/sec; 44 degrees latitude; emissivity 0.5; absorptivity 0.5, June 30 at 12 p.m.

Want to use this article? Click here for options!
© 2012 Penton Media Inc.


Acceptable Use Policy

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.

General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.

blog comments powered by Disqus

T&D TV

Most Read


Find Other Popular Items

Features

Vegetation Management
Grid Optimization

Upcoming Webcasts

Transmission & Distribution World allows you to access live and on-demand webcasts. Webcasts are available during their scheduled date and time. If you are unable to attend at the scheduled time, these free events will be available On-Demand for viewing at your convenience.


On-Demand Webcasts

» View More Webcasts

Jobzone
  • Transmission & Distribution World May 2012 Issue
  • Transmission & Distribution World April2012 Issue
  • Transmission & Distribution World March 2012 Issue
  • Transmission & Distribution World February 2012 Issue
  • January 2012 Issue
  • December 2011 Issue
  • November 2011 Issue

Browse Back Issues