Resources

Search, compare, and request quotes for nearly 13,000 products with detailed listings:

Blogs

  • 2012 IEEE PES Show Blog

    The IEEE Blog is a unique tour of the 2012 PES Expo in Orlando, FL, by Gene Wolf, former chairman of the IEEE PES T&D Committee.

White Papers

» More White Papers

Follow Power Editor Nikki Chandler on

Follow Technology Editor on Vito Longo

Find T&D World on Facebook

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

  
   

Taming Harmonics in Switzerland

During Severe System Disturbances in the Swiss Unterengadin Region, excessively high harmonic voltages have resulted in damage to some medium-voltage (MV) and low-voltage (LV) equipment. The MV subnetworks of the region are fed from substations supplied by the 380-kV transmission lines that tie Switzerland to Austria and Italy.

Measurements have shown that during certain network configurations, the 5th harmonic voltage content is close to the International Electrotechnical Commission's (IEC) harmonic limit level and the 7th harmonic voltage level exceeds the IEC's limit. Swiss utilities launched extensive studies to determine the exact cause of these problems, analyze the influencing factors and evaluate possible solutions.

THE PROBLEM

The Unterengadin region is situated in southeast Switzerland in the middle of the Alps. The regional distribution networks are fed from the 380-kV Pradella Substation, which is connected by a 380-kV overhead line to Sils, Switzerland, and the Swiss and European extra-high-voltage (EHV) transmission systems. In 1991, the EHV transmission system was extended with a double-circuit overhead line from Pradella to Westtirol in Austria. Figure 1 shows the EHV transmission and regional distribution systems.

Since this circuit was commissioned, harmonics in excess of IEC 1000-3-6 standard limits were occurring in the distribution networks of the Swiss Unterengadin during certain network configurations. In particular, high levels of 5th and 7th harmonic distortion (the latter being the highest) were recorded when the 380-kV Filisur-Sils line was disconnected; therefore, this was considered a critical circuit configuration. However, the voltage distortion was reduced when the hydropower plants in Pradella, Ova Spin and Martina were in service, and the harmonic current flow on the Westtirol intertie was unaffected.

Harmonic distortion was first recorded in the 1990s, when the 16-kV Samnaun network experienced occasional severe disturbances, resulting in damage to LV equipment including customer load control receivers and couplings. The problem has increased in recent years, prompting Swiss utilities to study this regional voltage pollution problem.

HARMONIC MEASUREMENTS

Continuous harmonic measurements on behalf of the regional utilities in various substations on the MV networks and in one substation on the 380-kV system have been made since 1995. All the measurement equipment has been connected to the LV side of the high-voltage (HV) or MV transformers. Hence, the measurement results are limited to the frequency range of 50 Hz to 500 Hz.

Figure 2 shows examples of the 7th harmonic voltage recorded at different locations between Aug. 3 to Aug. 31, 2004. Trace 3 in Fig. 2 shows the 7th harmonic course at the central 380-kV node of Pradella. With a value varying from near 0% to 4.4% maximum, the trace shows different levels — with the levels being superimposed by regular daily load variations — attributable to various system configurations. Under the normal network configuration, when all the 380-kV lines were energized, the specified 7th harmonic level of 2% was exceeded most of the time. Disconnecting one of the two parallel lines between Pradella and Westtirol did not significantly alter this level, but when both lines were de-energized, there was almost no 7th harmonic.

The maximum value of this harmonic occurred when the Schyn-N line was disconnected and all the other lines were energized. The harmonic voltage courses in the MV systems, the 10-kV Unterengadin (Trace 4, Gurlaina) and the 50-kV Davos (Trace 2) showed a very similar shape, whereas in the subordinate 25-kV system of Samnaun (Trace 1), which was equipped with a LV active filter for the 7th and 5th harmonics, the overall level was lower. An interesting fact is that the 7th harmonic level in the Samnaun network decreased with system voltage. However, before installing the active filter, values of 14% were recorded on the Samnaun 0.4-kV network.

Based on the harmonic measurement studies, the following conclusions were drawn:

  • The 2% acceptable 7th harmonic standard was exceeded during some circuit configurations on the 380-kV and 50/60-kV systems.

  • On the radially connected MV systems, 7th harmonic voltages of 6% to 9% were recorded, coincident in time with the maxima on the EHV system (unless damped by local filters).

  • ANALYSIS OF SYSTEM STUDIES

    The harmonic distortions occurred predominantly in the evening and at low load periods.

  • With the EHV lines to Westtirol disconnected, no 7th (and 5th) harmonic voltages appeared in the remaining EHV system and subordinate MV systems. Therefore, the harmonic sources (currents) stemmed mainly from the Westtirolean section of the system. These were attributable to wind-farm generators in Germany.

To verify the results taken during the measurement period and to study possible countermeasures, a three-phase electromagnetic transient model of the monitored EHV, HV and MV systems was developed. Transformers and overhead lines were modeled by means of frequency-dependent elements, and loads were modeled by series-parallel R-L-C equivalents. The complete model network comprising voltage levels from 380 kV to 6 kV was tested in sections and as a whole for load flow and short-circuits conditions.

NETWORK TOPOLOGY

Frequency scan calculations were performed, whereby a current of 1 A was injected into the central 380-kV node of Pradella, and the voltage response was determined for frequencies over a 10- to 1000-Hz range. For a normal system configuration with all the 380-kV lines connected, the first resonance (peak) was detected at about 325 Hz. However, when the current was injected near Westtirol, the first resonance shifted closely toward 350 Hz (7th harmonic). Figure 3 shows the frequency scan results for the 380-kV nodes Pradella and Filisur, a 50-kV node of the Davos network, a 60-kV node of the Unterengadin (Gurlaina) network and the 6-kV network of Samnaun when the Schyn-N line was disconnected. Injection of a 7th harmonic current of 10 A near Westtirol results in harmonic voltages of 7.7% of line voltage (13.3% of phase voltage) in Samnaun, matching the worst-case scenario.

Measurements in the Swiss Unterengadin region confirmed that during low load periods under certain network configurations, the 7th harmonic voltage level exceeded the IEC harmonic limit level, whereas the 5th harmonic voltage level remained close to the limit. For example, the 7th harmonic levels were recorded in the LV networks of Samnaun (14%), Gurlaina (8.8%) and Davos (6.5%), and in the EHV Pradella Substation (6.7%).

PASSIVE SHUNT FILTERS

The frequency scan analysis showed that the transfer impedances between the 380-kV Westtirol or Pradella nodes and the 16-kV Samnaun and 50-kV Gurlaina, Zernez and Davos nodes had a common parallel resonance peak at around 350 Hz. That meant a relatively small 7th harmonic current flowing on the 380-kV transmission line from Westtirol to Pradella could produce very high 7th harmonic voltages on the LV subnetworks connected to these substations.

The grid owners investigated four countermeasure techniques: changing the network topology, employing passive shunt filters, blocking series filters and installing active filters at strategic locations in the network.

Want to use this article? Click here for options!
© 2012 Penton Media Inc.


Acceptable Use Policy

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.

General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.

blog comments powered by Disqus

T&D TV

Most Read


Find Other Popular Items

Features

Vegetation Management
Grid Optimization

Upcoming Webcasts

Transmission & Distribution World allows you to access live and on-demand webcasts. Webcasts are available during their scheduled date and time. If you are unable to attend at the scheduled time, these free events will be available On-Demand for viewing at your convenience.


On-Demand Webcasts

» View More Webcasts

Jobzone
  • Transmission & Distribution World May 2012 Issue
  • Transmission & Distribution World April2012 Issue
  • Transmission & Distribution World March 2012 Issue
  • Transmission & Distribution World February 2012 Issue
  • January 2012 Issue
  • December 2011 Issue
  • November 2011 Issue

Browse Back Issues