Resources

Search, compare, and request quotes for nearly 13,000 products with detailed listings:

On Demand Media

Demand Viewing

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

Blogs

  • 2010 IEEE PES Show Blog

    The IEEE Blog is a unique tour of the 2010 PES Expo in New Orleans, LA, by Gene Wolf, former chairman of the IEEE PES T&D Committee.

White Papers

» More White Papers

Follow Power Editor Nikki Chandler on

Follow Technology Editor on Vito Longo

Find T&D World on Facebook

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.


  

Com Ed’s West Loop Project Entailed an Exacting Under-River Boring

Com Ed’s West Loop project had two main objectives: to add capacity and improve reliability by bringing 345-kV power underground into Chicago’s business district and to convert its transmission system to a network model (see Projects in Progress, 4-25-08). Both objectives have been achieved, but one major obstacle stood in the way – the Chicago River. The West Loop Substation is on an island in the North Fork of the Chicago River, called Goose Island. Two 345-kV circuits had to be brought to the island under the river.

As explained by Bruce Whiteway, program manager, “Construction vaults approximately 15 ft by 30 ft by 60 ft deep were dug on either side of the river. We lowered a boring machine into the vault and used it to tunnel from one side of the river to the island, a distance of approximately 300 ft. Pushing reinforced concrete pipe casings behind the drilling unit created a 5-ft inside diameter tunnel – one for each of the two transmission circuits.”

The pipe casings were then filled with 16 PVC pipes that run the full length of the tunnel (inside the concrete casing), held in place by bore spacers. The spacers support the PVC pipes in proper position to hold the 345-kV solid-dielectric transmission cables. The space between the pipes was backfilled with grout to make a solid duct package. The cables, once pulled through the ducts connect on one side to the gas-insulated switchgear on the island and into the ducts on the mainland that run under Chicago’s streets. Two more casings were also drilled and installed for future use.

“At one point we hit solid rock and had to blast,” said Whiteway, “but the delay only cost us three or four days with no serious consequences.”

Whiteway cited getting under the river four times with the casings as a major accomplishment. “The engineering and implementation of getting these tunnels under the river went very well. The contractor performed well. I was very pleased.”

Want to use this article? Click here for options!
© 2012 Penton Media Inc.

Most Read


Find Other Popular Items

Community

T&D World TV


Thomas & Betts - Collaboration. Commitment. Customer-Focus: Our promise to you. With over 50 years of pioneering design expertise and a partnership approach to every project, Thomas & Betts has a well-earned reputation as an innovator and a problem solver. Watch Now »


Siemens - Covering the entire spectrum of energy automation. Watch Now »

Podcasts

Building a Smarter Grid: Managing Assets to Improve Utility Decision Making
Sponsored by ABB
Join Greg Scheu, President and Head of Power Products for ABB, and Rick Bush as they discuss how utilities can extract more value from existing grid infrastructure by managing the overall assets of the T&D operation. Listen Now »

More from Building A Smarter Grid


Electromagnetic Pulse Discussion with Eric Hsieh
NEMA Government Relations Manager Eric Hsieh discusses an EMP and its possible effects on the electric grid.

Jobzone
  • January 2012 Issue
  • December 2011 Issue
  • November 2011 Issue
  • October 2011 Issue
  • September 2011 Issue
  • August 2011 Issue
  • July 2011 Issue

Browse Back Issues