Resources

Search, compare, and request quotes for nearly 13,000 products with detailed listings:

Blogs

  • 2012 IEEE PES Show Blog

    The IEEE Blog is a unique tour of the 2012 PES Expo in Orlando, FL, by Gene Wolf, former chairman of the IEEE PES T&D Committee.

White Papers

» More White Papers

Follow Power Editor Nikki Chandler on

Follow Technology Editor on Vito Longo

Find T&D World on Facebook

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

  
   

Ireland’s EirGrid Submits Planning Application for Meath-Tyrone 400-kV Interconnection Development

EirGrid is submitting a planning application to An Bord Pleanála under the Strategic Infrastructure Act for the Meath – Tyrone 400-kV Interconnection Development, which will facilitate cross-border sharing of electricity and ensure the long-term secure supply of electricity for the North East.

The route being submitted for planning approval runs from Woodland, Co. Meath to Lemgare, Co. Monaghan and includes a proposed new substation at Moyhill, Co Meath. This route was defined in earlier route selection studies as Route 3B from Meath to Cavan and Route A from Cavan to Tyrone.

The Environmental Impact Statement (EIS) submitted to the Board will be available for statutory public consultation for 10 weeks, from Jan. 4 to March 12. The application and EIS will be available on a new dedicated website, www.eirgridnortheastprojects.com.

“We have proposed an extension of the statutory public consultation by three weeks because of Christmas and while the EIS was available to download and to view throughout Christmas, the public consultation formally began on January 4th,” says Tomás Mahony, Project Engineer, EirGrid. “We encourage people to come into the EirGrid Information Centers in Navan and Carrickmacross to view the documents and to meet members of our team who can clarify any questions they may have – we will be on the ground in the Navan and Carrickmacross Information Centers in January and February, or by appointment.”

In the course of examining options for this project and for the development of the transmission system generally, EirGrid has carried out extensive technical and economic analysis and has reviewed international practice and experience.

One of the issues frequently raised is the possibility of developing an underground cable solution. Having carried out detailed analysis and having reviewed a wide range of international material, EirGrid has concluded that with the current state of technology it is simply not practical to develop an underground solution for this project today.

“Internationally there is a reasonable level of experience of underground development at lower voltages,” says Tomás Mahony. He adds: “However at 400 kV, the voltage required for this project, many of the technical challenges have not been overcome and there are no underground cable developments anywhere in the world at this scale and voltage. EirGrid concludes that attempting to develop this project on an underground basis would at best be a high-risk experiment, which may well result in failure, could waste many hundreds of millions of customer’s money and would jeopardize security of supply to the north-east region and indeed to the electricity system throughout Ireland.”

The analysis carried out by EirGrid includes a study by PB Power, which looked at the engineering, environmental and cost issues associated with undergrounding a project of this nature. The report concludes that overhead power lines are the cheapest and most secure option for the planned power lines in the North East. These findings are very much in line with a wide range of reports carried out internationally by transmission system operators and government authorities, including the Ecofys report commissioned by the Department of Communications Energy and Natural Resources.

EirGrid also commissioned Tokyo Electric Power Co. (TEPCO), which has installed and operates the longest 500-kV underground cable in the world at 40 km, to examine the potential for installing high voltage underground cable in the Irish system, ignoring cost and environmental issues.

The TEPCO Report confirms that there are a number of serious technical challenges involved in installing an underground cable of this type and length. EirGrid concludes, based on a review of the TEPCO report and other inputs, that there are huge risks which would accompany a project on this scale.

TEPCO is one of a suite of reports being published in conjunction with the submission of the planning application to An Bord Pleanála. The reports are mainly technical in nature and are available on www.eirgrid.com.

“EirGrid does not intend to propose an underground solution which is clearly technically inferior, would cost at least hundreds of millions of Euros more than an overhead line solution and which ultimately may well fail, thus putting security of electricity supply at significant risk,” says Tomás Mahony.

Want to use this article? Click here for options!
© 2012 Penton Media Inc.


Acceptable Use Policy

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.

General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.

blog comments powered by Disqus

T&D TV

Most Read


Find Other Popular Items

Features

Vegetation Management
Grid Optimization

Upcoming Webcasts

Transmission & Distribution World allows you to access live and on-demand webcasts. Webcasts are available during their scheduled date and time. If you are unable to attend at the scheduled time, these free events will be available On-Demand for viewing at your convenience.


On-Demand Webcasts

» View More Webcasts

Jobzone
  • Transmission & Distribution World May 2012 Issue
  • Transmission & Distribution World April2012 Issue
  • Transmission & Distribution World March 2012 Issue
  • Transmission & Distribution World February 2012 Issue
  • January 2012 Issue
  • December 2011 Issue
  • November 2011 Issue

Browse Back Issues