Strathalbyn Power Supply Upgrade to Meet Increasing Demand
ETSA Utilities, South Australia, is responding to growth in the Strathalbyn area, with a $1.3 million investment to upgrade the Strathalbyn substation. The substation currently serves about 7,500 customers. General Manager, Services, Sue Filby, said local customer demand had been growing by 3.3 percent per annum since 2000-2001. "We're expecting even higher growth in the next five years due to residential developments and support for the new Terramin mine at Strathalbyn East.
"ETSA Utilities monitors current and future demand to ensure we keep up with the economic growth of the state. It's exciting to see Strathalbyn sharing in the state's growth," she said.
ETSA Utilities will install a 10-MVA, 66/11-kV transformer, as well as new 66-kV and 11-kV circuit breakers at the substation.
Filby said the development was part of a $166 million investment in the South Australian electricity distribution network in 2008. New power lines are being added to the network, substations upgraded and hundreds of street transformers replaced.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus