AREVA Signs 67-Million Euro Contract in Saudi Arabia
AREVA’s Transmission and Distribution (T&D) division has signed a turnkey contract to build a high-voltage substation in Saudi Arabia for an Independent Water and Power Project (IWPP) lead by the Shuqaiq Water and Electricity Co. The 67-million euro contract was awarded by the project Engineering Procurement Contractor, Mitsubishi Heavy Industries.
The Jizan region in southern Saudi Arabia is undergoing considerable economic development resulting in an increased demand in electricity. To secure the region’s supply, the government is boosting its generation capacity by building a new power plant and water desalination unit in Shuqaiq, near Jizan. AREVA T&D’s 400/132-kV substation will feed the plant’s 850-MW of electricity onto the 400-kV transmission grid ensuring a steady flow of electricity to local industries.
Under the contract, AREVA T&D will also supply associated control and protection systems as well as engineering, erection and commissioning works.
The substation is scheduled for delivery by April 2009.
Michel Augonnet, Executive Vice-President of AREVA T&D’s Systems Business Unit said: “We were awarded this contract against fierce competition due to our optimal project delivery time, recognized reactivity and longstanding expertise.”
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus