ATC Receives Approval to Rebuild Transmission Line
The Public Service Commission of Wisconsin has approved American Transmission Co.’s application to rebuild the 18-mi, 69kV electric transmission line that connects the Brodhead Substation and South Monroe Substation in Monroe. The new line will make a vital improvement in the reliability of the electric transmission system serving the area. The age and condition of the existing line necessitated the rebuild.
“This project will not change the voltage of the line,” says Charlie Gonzales, ATC local relations representative, “but the replacement structures will be designed to accommodate potential upgrades that might be needed in the future to support growth in the area.”
The new line will follow the route of the existing line, and the work will involve installing new poles, wires and insulators. Construction is scheduled to begin late next year and is projected to continue through summer 2011.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus