Con Edison Announces New Electric Delivery Investments
Consolidated Edison Co. of New York, Inc. (Con Edison) announced that the company is filing new electric rate and investment plans with the New York State Public Service Commission (PSC) to begin April 1, 2009.
Adding another phase to the company’s EnergyNY plan, the rate proposal seeks to address the long-term energy infrastructure investment requirements of New York City and Westchester County, while establishing new permanent demand-reduction and energy-efficiency programs.
As part of the its overall three-year $5.5 billion capital program to enhance electric delivery infrastructure, Con Edison is planning the following investments:
- Construct and energize one new transmission station, three new area substations -- $633 million;
- Install 3,100 miles of high voltage distribution cable -- $567 million;
- Install 3,000 miles of low voltage distribution cable -- $576 million;
- New/replace/upgrade 16 transmission feeders -- $387 million;
- Install 4,500 distribution transformers and six substation transformers and equipment -- $957 million; and
- Replace 600 miles of overhead wire, increase overhead reliability for storm resilience and coastal flood mitigation -- $160 million.
In addition, continued growth in energy demand will require four new substations to be completed over the next three years, and a total of 10 new substations to be constructed over the next decade.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus