NPPD Board Approves T&D Infrastructure Projects
The Nebraska Public Power District approved a number of capital projects at its regular September meeting to refurbish and upgrade transmission and distribution infrastructure, some of which had been damaged in spring storms.
The Board approved the following capital projects:
- 115-kV substation refurbishment at Canaday Station
- Bloomfield-Gavins Point 115-kV transmission line refurbishment
- Hastings 230-kV substation refurbishment and 115-kV capacity upgrade
- Ord 115-kV substation capacity upgrade
- Distribution pole replacement projects for 2008 at various locations
- Sub-transmission line spring storm damage restoration
- Distribution line spring storm damage restoration
- Extra high voltage line spring storm damage restoration
- High voltage line spring storm damage restoration.
Also approved were the following customer services and delivery items:
- Contract for 115-kV transmission line refurbishment from Bloomfield - Gavins Point, awarded to TESSCO Utility Services, Inc.
- Contract for Hastings 230-kV Substation addition and modifications was awarded in three parts to TESSCO Utility Services, Inc.
- Contract for relay/control panels for Canaday Station awarded to Schweitzer Engineering Laboratories, Inc.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus