660 kV HVDC Success in China
As of Nov. 28, 2010, Pole 1 of State Grid Corporation of China’s (SGCC) Ningdong-Shandong 660 kV HVDC connection has full 2000 MW power for commercial operation. This is a great milestone for Alstom Grid and our Chinese partner, CEPRI, to demonstrate our strong capability and teamwork in this project.
This project has been full of world records: i.e., 660 kV voltage, single 12-pulse bridge per pole, large cross section line of 1000 mm², transmission distance of 1335 km, and a centralized control and protection system.
“Long-distance HVDC connections at voltages above 500 kV will become more frequent around the world, connecting large power generation sites with distant load-centers,” stated Michel Augonnet, Senior Vice President, Alstom Grid. “Alstom Grid is very proud to have been selected to work with SGCC and CEPRI on these important projects as they underline the viability of our HVDC thyristor valve technology at ultra-high voltages.”
According to SGCC, Pole 2 is on schedule for commercial operation by the end of February 2011. This contract was signed in May 2009 together with another contract for the HVDC interconnection from the Three Gorges Dam to Shanghai.
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus