Resources

Search, compare, and request quotes for nearly 13,000 products with detailed listings:

On Demand Media

Demand Viewing

Transmission & Distribution World On Demand events allow you to access archived webinars when it is convenient for your schedule. These free events are available for viewing 24/7.

Blogs

  • 2012 IEEE PES Show Blog

    The IEEE Blog is a unique tour of the 2012 PES Expo in Orlando, FL, by Gene Wolf, former chairman of the IEEE PES T&D Committee.

White Papers

» More White Papers

Follow Power Editor Nikki Chandler on

Follow Technology Editor on Vito Longo

Find T&D World on Facebook

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.


  

Special Plan to Rebuild 115-kV Transmission Line Keeps Lines Energized Most of the Time

In mid-December Henkels & McCoy completed Phase One of the Plumtree to Triangle 115-kV Rebuild Project in western Connecticut for Northeast Utilities. The project is replacing 16, 115-kV lattice steel towers with 32 steel monopole structures. New conductor and OPGW (optical ground wire) over 1.8 miles of right of way (ROW) will be strung. Two new monopoles will replace each lattice tower. For the duration of the project, keeping the lines energized except for those times when it is absolutely necessary to have an outage to perform the work has presented a unique challenge. The lines had to be de-energized, for example, when conductors were moved from the old structure to the new poles, and when new conductor was being pulled in. But most of the time when the work was being done the lines had to remain energized.

The original lattice steel structures held three separate 115-kV circuits: Two circuits on the outer arms and one circuit in the center space. The rebuild project will replace these circuits with just two circuits comprised of heavier conductors which will be mounted one each on the two new rows of monopole towers. The original conductors were 397.5 kcmil ACSR and 556.5 kcmil ACSR. The new conductors will be 1272 kcmil ACSR. According to Henkels & McCoy construction manager Danny Ashmore, each lattice structure will be replaced by two steel poles: one slightly to the north of the existing structure on the same ROW and one slightly to the south of the existing structure.

Work started in July 2006, first with construction of the tower foundations on the north and south sides of existing structures; then with installation of the monopole towers on the north side only, all with the lines energized. Ashmore said, “In the final configuration there will be two monopoles with arms tipped in toward the existing lattice structure which will then be removed.”

To arrive at that final arrangement, however, a temporary line was needed. As Ashmore explains: “We built the north side towers with arms going out in both directions. Then we installed a temporary line on the furthest outside arms. Next we transferred the existing conductor from the lattice structure to the inside arms of the tower and removed the lattice structure arms (see photo). For safety reasons this move was done with the line de-energized. Now with the two lines installed on the tower, we can remove the center and south side lines from the lattice structures and dismantle them. In Phase Two, we will build the south side monopole towers, install the south side lines, and then remove the temporary lines on the outside of the north towers.”

Safety is a prime concern for the contractor on this project, so potential safety problems and danger areas were identified and appropriate work procedures developed. In addition, Ashmore explained, “We have a special safety plan with respect to the demolition of the lattice structures because of constraints such as terrain and the fact that the line traverses residential neighborhoods.”

Work is expected to be complete by spring 2007.

Want to use this article? Click here for options!
© 2012 Penton Media Inc.

T&D TV

Most Read


Find Other Popular Items

Community

T&D World TV


Thomas & Betts - Collaboration. Commitment. Customer-Focus: Our promise to you. With over 50 years of pioneering design expertise and a partnership approach to every project, Thomas & Betts has a well-earned reputation as an innovator and a problem solver. Watch Now »


Siemens - Covering the entire spectrum of energy automation. Watch Now »

Podcasts

Building a Smarter Grid: Managing Assets to Improve Utility Decision Making
Sponsored by ABB
Join Greg Scheu, President and Head of Power Products for ABB, and Rick Bush as they discuss how utilities can extract more value from existing grid infrastructure by managing the overall assets of the T&D operation. Listen Now »

More from Building A Smarter Grid


Electromagnetic Pulse Discussion with Eric Hsieh
NEMA Government Relations Manager Eric Hsieh discusses an EMP and its possible effects on the electric grid.

Jobzone
  • Transmission & Distribution World May 2012 Issue
  • Transmission & Distribution World April2012 Issue
  • Transmission & Distribution World March 2012 Issue
  • Transmission & Distribution World February 2012 Issue
  • January 2012 Issue
  • December 2011 Issue
  • November 2011 Issue

Browse Back Issues