California’s Grid Plan Ready for Renewable Power Influx
The California Independent System Operator Corp. (ISO) Board of Governors has approved the 2010-2011 Transmission Plan that includes 33 grid upgrades for addressing future reliability and policy-driven needs worth $1.2 billion. The approval provides a timely decision that will aid renewable power projects seeking financing. The ISO accelerated its planning process by six months so that American Recovery and Reinvestment Act projects could meet eligibility criteria.
The plan demonstrates that the transmission infrastructure approved to date by the ISO is adequate to carry thousands of new megawatts to meet the nation’s most ambitious renewable resources goal. The transmission projects that are already approved through the ISO planning process, or identified in large generator interconnection agreements, or are progressing through the CPUC approval process accommodate a diverse range of resource portfolios for meeting a 33% RPS.
“The finding that no major new transmission projects are needing approval by the ISO at this time to support RPS reflects years of effort by the ISO, state agencies, the California Transmission Planning Group, participants in the Renewable Energy Transmission Initiative and market participants that resulted in the approval and ongoing construction of major transmission projects such as Tehachapi and the Sunrise Powerlink,” said Vice President of Market and Infrastructure Development Keith Casey, Ph.D.
The need for access to renewable resources in Imperial County created the need for the first policy-driven transmission project—a category enabled by the ISO’s new transmission planning process approved by FERC last December. The project involves re-conductoring the Devers-Mirage 230 kV double circuit line (Path 42), located in the Southern California Edison transmission service territory.
The ISO recognizes that uncertainty remains regarding how California will ultimately meet its 33% RPS goals in terms of the precise locations, resource mix and quantity of renewable energy resources. While this plan shows that the transmission approved to date can accommodate a diverse range of plausible renewable development, the ISO will continue to work with state agencies and all stakeholders to evaluate development trends and policy directives beginning with next year’s planning cycle, and will reassess the transmission needs accordingly.
This is first comprehensive ISO grid plan that considers projects that meet the California’s 33% RPS as well as reliability upgrades and economic additions that benefit ratepayers. The revised transmission planning process, developed in close collaboration with stakeholders, was approved by federal regulators in December 2010
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus