Tdworld 3451 Offshorewind2

Siemens Receives Order for Offshore Wind Power Plant in UK

Nov. 13, 2015
56 wind turbines of the six-megawatt class for the Galloper project Siemens Financial Services to hold 25 percent of the total equity in Galloper Wind Farm Ltd. Output of 336 megawatts to supply up to 336,000 British households Long-term maintenance contract

Siemens is to supply, install and commission 56 wind turbines for the Galloper Wind Farm Ltd. (GWFL) off the southeast coast of England. The owners of the offshore wind power plant are RWE, UK Green Investment Bank, Macquarie Capital and Siemens Financial Services (SFS), each with a 25 percent stake. The plant’s 336 megawatt capacity will be sufficient to supply up to 336,000 British households with clean power. Siemens will also be responsible for servicing the wind turbines for a 15-year period. The total investment costs of the Galloper project are 1.5 billion British pounds.

The company is working on various levers to reduce the cost of offshore wind power still further. As early as 2020, Siemens aims to have technologies available that will make it possible to generate electric power at a cost of less than 10 Euro cents per kilowatt hour. Improvements will be made not only to the wind turbines themselves; the company is also focusing on innovations in connecting the offshore installations to the grid and in servicing.

Siemens is due to start installing the 56 SWT-6.0-154 wind turbines for the Galloper project in May 2017. The wind power plant is scheduled to be fully operational by March 2018. Prompt completion is necessary so that the offshore project can still qualify for remuneration with ROC (Renewable Obligations Certificates) of the 2.5 round for public tenders.

Siemens Financial Services contributed to securing the Siemens bid by providing 25 percent of the total project equity, as well as supporting RWE with development funding in the period up to financial close. “The speed in which we achieved financial close, which included securing debt investments from a club of commercial lenders, is testament to the market’s appetite for well-structured offshore wind investments and its confidence in Siemens’ technical and financial expertise in this sector,” commented Kirk Edelman, Head of Energy Finance at Siemens Financial Services.

The Galloper offshore wind power plant is to be erected around 27 kilometers off the coast of Suffolk. The wind turbines will be constructed on monopiles in water between 27 and 36 meters deep.

The Galloper project is an extension of the already on-line Greater Gabbard offshore wind farm, which has a capacity of 504 megawatts, where 140 Siemens wind turbines have been generating power for 530,000 British households since 2012.

Siemens has already erected an offshore capacity of more than 5.8 gigawatts worldwide, with two gigawatts commissioned in the last fiscal year alone. The UK is one of the major offshore markets. Siemens employs about 2,000 people across various sites in Britain in the wind business, grid connections and wind service operations. The Galloper project is set to create around 700 jobs during construction and 90 jobs once operational in the UK. It also represents a crucial milestone in the creation of a UK-based offshore wind manufacturing industry, begun with a 160 million pounds investment from Siemens in setting up a rotor blade manufacturing in Hull and continuing through job creation both by Siemens and the supply chain developing to support the clean energy industry.

Voice your opinion!

To join the conversation, and become an exclusive member of T&D World, create an account today!