Resources

Search, compare, and request quotes for nearly 13,000 products with detailed listings:

Blogs

  • 2012 IEEE PES Show Blog

    The IEEE Blog is a unique tour of the 2012 PES Expo in Orlando, FL, by Gene Wolf, former chairman of the IEEE PES T&D Committee.

White Papers

» More White Papers

Follow Power Editor Nikki Chandler on

Follow Technology Editor on Vito Longo

Find T&D World on Facebook

News Releases

Briefing Room

At the Briefing Room you will be able to stay up-to-date on the latest technology announcements where we will provide daily postings from our industry sources.

  
   

Megawatts of Solar

Initial megawatt-scale rooftop systems will lead to a massive addition of photovoltaic to the distribution grid.

Southern California Edison is Leading California's Charge to meet the nation's most ambitious renewable portfolio standard (RPS) targets: 20% by 2010 and even higher in years ahead. To satisfy these aggressive targets, Southern California Edison (SCE; Rosemead, California, U.S.) has taken the initiative to add a planned 250 MW of new photovoltaic (PV) resources to its system.

While PV is a recognized and well-understood renewable resource, its development and deployment on a massive scale is an emerging and evolving practice. Another challenge is the cost of PV. Through SCE's PV program, costs could be driven down to reach US$3.50/W.

The first 2.44-MW installation of the initiative has been built and is currently providing virtually greenhouse-gas-free power to the grid. The experience and knowledge gained from this installation will help accelerate the commercial viability of PV, a critical component to the green goals of SCE, the state of California and the U.S.

FONTANA ROOFTOP PROJECT

SCE's completed 2.44-MW Fontana rooftop project is the first of many 1-MW to 2-MW systems that, in aggregate, will comprise SCE's proposed Solar Photovoltaic Program (SPVP). SCE is seeking approval from the California Public Utilities Commission (CPUC) to build and own 250 MW of PV, installed in the sunny eastern area of SCE's service territory, primarily in 1-MW to 2-MW systems, on top of huge warehouse rooftops. If the opportunity were to arise, SCE would consider constructing PV on rooftops that could accommodate systems larger than 2 MW, or even on a few ground-mounted systems.

The renewable-resource generating units in SCE's SPVP will be close to customer load centers and connected directly to the utility's distribution grid, thereby avoiding the extra cost (capital facilities and electrical losses) of delivering remote green power to load centers. The Fontana site is one of three pilot projects SCE is building in advance of the CPUC's final decision on the full program.

In selecting sites, SCE looks for roofs that are less than five years old and greater than 300,000 sq ft (27,871 sq m) on buildings that have little on-site load and are owned by a company or real estate trust, preferably with a portfolio of candidate buildings.

From a grid standpoint, the location must be served by a primary distribution circuit with the electrical characteristics to receive the PV-generated power.

The Fontana project site fit these criteria. The host building's rooftop is 600,000 sq ft (55,742 sq m), has little on-site load and is owned by ProLogis, one of the world's largest owners and developers of warehouse and industrial space. ProLogis served as general contractor during the construction of the Fontana PV unit on this building.

The PV array was designed and engineered by First Solar Inc. (Tempe, Arizona, U.S.). The array uses First Solar's FS 272 modules — cadmium telluride (cad-tel) thin-film products. The equipment used to convert the PV array's DC output to AC for delivery to the grid was designed and built by Satcon Technology Corp. (Boston, Massachusetts, U.S.). The project used four of Satcon's 500-kW Generation II inverters. The aggregate 2-MW (AC) output is stepped up to 12.4-kV primary distribution voltage through SCE's standard distribution switchgear and transformer.

ProLogis applied for construction permits with the local permitting authority. However, no permitting fees were required for the Fontana site, because the permitting authority had zoned this area to encourage construction of renewable green power. Approval by the local fire authorities was a bit more challenging, as PV is a relatively new technology to them, and PV safety coordination procedures with the utility and PV labeling standards had not been definitively specified. In the end, satisfactory solutions were negotiated with the permitting and fire authorities.

Gregg Electric Inc. (Ontario, California) performed the construction under a participating labor agreement with the International Brotherhood of Electrical Workers Local 47. Construction of the 2.44-MW unit took 60 days to complete.

The facility was commissioned on Dec. 1, 2008, by California Gov. Arnold Schwarzenegger and Ted Craver, chairman and CEO of SCE's parent company, Edison International.

Want to use this article? Click here for options!
© 2012 Penton Media Inc.


Acceptable Use Policy

Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.

General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.

blog comments powered by Disqus

T&D TV

Most Read


Find Other Popular Items

Features

Vegetation Management
Grid Optimization

Upcoming Webcasts

Transmission & Distribution World allows you to access live and on-demand webcasts. Webcasts are available during their scheduled date and time. If you are unable to attend at the scheduled time, these free events will be available On-Demand for viewing at your convenience.


On-Demand Webcasts

» View More Webcasts

Jobzone
  • Transmission & Distribution World May 2012 Issue
  • Transmission & Distribution World April2012 Issue
  • Transmission & Distribution World March 2012 Issue
  • Transmission & Distribution World February 2012 Issue
  • January 2012 Issue
  • December 2011 Issue
  • November 2011 Issue

Browse Back Issues