Substation Expansion Goes Vertical
Compact substation design makes the most of available space in Shanghai's central districts.
In Shanghai, China, the existing 35-kV substations are located indoors on large sites, and the operation and maintenance costs are relatively high. The design and development of composite switchgear technologies have resulted in wide-scale application of 35-kV and 10-kV SF
To standardize substation equipment specifications, construction, operation and maintenance in order to improve the economic efficiency and simplify the equipment tendering process, the State Power Grid Co. (SPGC) invited several design companies to study and produce a SPGC manual for 35-kV substations. This manual now forms the specification for the design of 35-kV B5-type substations in the Shanghai power grid.
New Compact Design
A new compact design has been adopted for new substations, where available land is limited, and for substations in some central districts of Shanghai, where available sites are generally irregular in shape. For these situations, composite switchgear provides the optimum solution. Based on the premise of accepting a moderate increase in the height of the building, there are two main methods to reduce the land area occupied by a substation:
-
Separate the transformer tank and the cooling radiator by vertical disposition. Applications of vertically displaced transformer cooling radiators include the Caoyang, Changqiao and Jingshajiang 35-kV substations in Shanghai.
-
Compact Distribution Transformers
Select compact 35-kV and 10-kV switchgear. For example, SF
6-insulated switchgear requires less space for operations staff.
The selection of distribution transformers available for 35-kV applications according to the type of insulation can generally be classified as dry-type, SF
Based on the production technology of most domestic transformer manufacturers at present, the maximum capacity of a dry-type transformer is 16 MVA, which can be increased to 20 MVA by fitting fans. There are examples of 20-MVA dry-type transformers in successful operation in Shanghai, such as in the Shanghai South Railway Station's 35-kV substation. However, the Shanghai power system planning standard specification for the transformer rating is 31.5 MVA for all new 35-kV substations.
There are very few SF
Oil-insulated transformers have the advantages of good insulation, improved cooling and a moderate price. They are widely used. The cost of SF
In accordance with the disposition of the transformer's tank and the cooling radiator, oil-insulated transformers can be classified as integrated, separated with horizontal or vertical disposition. Vertical disposition requires the least land occupation as the transformer's radiator is positioned above the transformer room, so the area of land required is limited to the dimensions of the transformer room.
Switchgear Selection
Based on past experience, if the integrated disposition is selected, the transformer room requires natural ventilation or a fan-induced ventilation attic for heat dissipation. This can result in low-frequency noise emission through the ventilation, making it difficult to comply with Shanghai's noise-level restrictions of 55 dB during the day and 45 dB at night. When the transformer and radiator are separated, the transformer is totally enclosed in a room that can be coated with noise-absorbent material, reducing noise emission to within acceptable environmental levels. Although the radiator room opens to the outdoors, any radiator noise emitted can be controlled to below 45 dB. Therefore, the optimized compact design scheme is based on an oil-insulated transformer with the tank and radiator vertically disposed.
Composite switchgear technology is now mature and extensively adopted for 35-kV and 10-kV indoor substations. The choice of switchgear is limited to GIS and air-insulated switchgear (AIS).
When AIS is selected, the width of the operational corridor between two facing switchboards is twice the space required to withdraw a single circuit breaker for maintenance plus an additional 900 mm (35 inches). In practice, the operational corridor used in SGPC's typical design of 35-kV Shanghai substations, equipped with two facing switchboards, should be 3000 mm (10 ft). Furthermore, the standard design scheme specifies the width of the maintenance corridor behind each switchboard, and the width of the switchroom for 35-kV and 10-kV substations is 11,000 mm (36 ft).
Transformer and Switchgear Interconnection
When SF
The interconnection between the 35-kV SF
It is apparent that the cost of connection between the transformer and switchgear is lower with the use of cable than it would be using SF
Compact vs. Typical Design
Also for the compact design, the main transformer room and the 35-kV and 10-kV switchroom are situated on the first floor, with the vertically displaced radiator in the capacitor room together with the station service transformer room on the second floor and the control room on the third floor. The indoor substation also includes a half-underground cable floor used as the substation entrance and for incoming and outgoing underground cables. The capacitors are installed to provide reactive power compensation to improve the power factor.
To construct city center substations, it is important to make the best use of the available land. The land required for the optimum compact 35-kV substation is 46% less than that for the typical design. This significant reduction alleviates the problem of securing favorable substation sites in the metropolitan central districts, where there is a shortage of land. At present, there are no land charges applicable to substation sites.
Substations based on the optimum compact design concept require less land, but the overall cost is higher than the typical design because they use the latest technologies, which require less in-service maintenance. The capital cost of the equipment for the two design schemes reveals the equipment cost for optimum compact substations is 4.65 million yuan (RMB), or 30%, more than for the typical standard design.
Shanghai Power Grid Co. has already adopted some of the recommended compact standards by installing substations with the transformer horizontally displaced and some substations equipped with SF
Wenliu Zhuang (zhuangwl@sepd.com.cn) graduated in 2001 from the Shanghai Electric Power Institute, where he majored in electrical engineering and automation. He then joined the Shanghai Electric Power Design Institute, where he worked as a design engineer on power transmission and substation projects. His current focus is mainly linked to substation design. In 2008, Zhuang earned the title of a national registered electrical engineer.
| Voltage | Means of connection | Specifications | Estimated cost (RMB) | Maintenance requirement | Application |
|---|---|---|---|---|---|
| 35 kV | SF |
1250 A | 28,000 | Non-maintenance | Few |
| Cable | 2 × (3 × 400) sq mm | 2164 | Few | Common | |
| 10 kV | Insulated bus bar | 3150 A | 18,000 | Few | Few |
| Cable | 3×3×(1×630) sq mm | 5310 | Few | Common |
| Item | B5-type substation design | Optimum compact substation design | |
|---|---|---|---|
| Main transformer capacity | 2 or 3 rated 31.5 MVA | 2 or 3 rated 31.5 MVA | |
| Outgoing circuits | 35 kV | 2 or 3 feeders | 2 or 3 feeders |
| 10 kV | 20 feeders | 20 feeders | |
| Means of connection | 35 kV | Overhead line connected to 35-kV transformer by a circuit breaker | Overhead line connected to 35-kV transformer by a circuit breaker |
| 10 kV | Single bus bar with bus sections | Single bus bar with bus sections | |
| 10-kV reactive power compensator | Shunt capacitors 2 × 4800 MVAR or 3 × 4800 MVAR | Shunt capacitors 2 × 4800 MVAR or 3 × 4800 MVAR | |
| 10-kV grounding/earthing mode | Resistance | Resistance | |
| Distribution equipment | 35 kV | Indoor single switchboard | Indoor single switchboard |
| 10 kV | Indoor double-row switchboard | Indoor double-row switchboard | |
| Disposition | All indoor, single building | All indoor, single building | |
| Type of main transformer | Transformer tank and radiator in horizontal disposition | Transformer tank and radiator in vertical disposition | |
| Land area occupied by substation | 754.72 sq m (21.2 m × 35.6 m) | 411.60 sq m (14.0 m × 29.4 m) | |
| Capital cost of equipment (for phase No. 1) | 15.55 million yuan (RMB) (US$2.278 million) | 20.2 million yuan (RMB) (US$2.960 million) | |
| Item | B5-type design scheme | Optimum compact design scheme | ||
|---|---|---|---|---|
| Equipment | Cost (RMB) (US$) |
Equipment type | Cost (RMB) (US$) |
|
| 35-kV main transformer tank and radiator | In horizontal disposition | 5,650,000 827,802 |
In vertical disposition | 6,550,000 959,665 |
| 35-kV switchgear | Cabinet | 930,000 136,258 |
GIS | 1,700,000 249,073 |
| 35-kV switchgear | Cabinet | 4,800,000 703,266 |
GIS | 7,570,000 1,109,109 |
| Connection between switchgear and transformer | Enclosed cable | 140,000 20,512 |
Cable | 350,000 51,280 |
| Total | 11,520,000 1,687,838 |
16,170,000 2,369,127 |
||
Want to use this article? Click here for options!
© 2012 Penton Media Inc.
Acceptable Use Policy
Comments are the sole responsibility of the person posting them. T&D World will not edit postings. If T&D World editors deem any comment inappropriate, we will preempt or remove the posting.
General Rules: T&D World will not allow comments that are found to be degrading based on gender, race, class, ethnicity, national origin, religion, sexual orientation or disability. Neither will epithets, abusive language or obscene comments be allowed.
blog comments powered by Disqus
















