Ontario Board Approves Construction of Transmission Facilities in Brampton
The Ontario Energy Board has issued a Decision and Order granting Hydro One Networks Inc. permission to construct electricity transmission facilities in the City of Brampton.
The project is intended to deal with overloading on the supply circuits to the Jim Yarrow Municipal and the Pleasant Transformer Stations and to bring the transmission system in that area to within IESO power delivery guideline limits. The proposed service date for the project is June 2009.
In its Decision, the Board noted the transmission reinforcement will improve the voltage performance of the west Brampton power system and generally increase power delivery and system reliability in that area.
Based on the evidence provided, the Board determined the proposed facilities are in the public interest.