Furthermore, maintenance work was conducted on the substation's components. The director of Substations East, Luis Miranda, said that the transformer was tested to monitor the condition of the internal and external parts and that it complies with the manufacturer's parameters. In addition, tests were carried out on the distribution switches and the battery bank, which are critical equipment that support the reliable operation of the substation.
“All these works that we carry out in the substation minimize the possibility of failures in the equipment, benefiting the 5,000 clients we have in the island municipality,” highlighted Miranda.
These works join the improvements that have recently been made to the 3100 transmission line, specifically in the section from Fajardo to the Daguao substation in Naguabo from where the 34 kV submarine cable to Vieques and Culebra leaves. On this line, changes were made to the hardware, which supports the conductors for the durability and resilience of the line. The ceramic insulators were also replaced with polymer, a lighter material that provides greater durability.
Meanwhile, on line 36200, in the section from the Río Blanco substation to Daguao, in addition to maintenance work, such as changing the hardware and insulation, vegetation clearing work was also carried out.
“The work carried out this weekend in Vieques is part of our commitment to modernize and maintain the 300 substations throughout Puerto Rico to make the electric grid more reliable and resilient,” Miranda said.
These efforts are in addition to the work completed on streetlights in the island municipality that began this year. So far, over 750 luminaires have been replaced with LED equipment that offers greater efficiency and resilience. Of these, 93 are amber or red lights to promote the safe nesting of sea turtles. Since the summer of 2022, LUMA has replaced more than 125,000 streetlights across Puerto Rico.