With the circuits and infrastructure supported by equipment that’s more than a century old, the current towers are nearing their end of life. To ensure continued reliability and resiliency, lineworkers are replacing 99 transmission towers with weathered steel monopoles over a 14.5-mile stretch between the Brunot Island and Crescent Township substations in DLC’s territory.
Modernizing the Line
After securing approval from the appropriate regulatory agencies, DLC and its construction contractor kicked off the five-phase BI-Crescent Transmission Project on Dec. 13, 2021. As of June 2022, the first phase of the project was complete, and the crews were moving into the next four phases of construction. Because the line crosses through congested urban areas, the line crews are working during off-peak load sections of the year like the fall and winter months.
With the line scheduled to be energized in 2027, work is now underway to replace the towers. A significant portion of the early phase of the project was to create and build access roads and work pads to the site. To make the construction site safer and work methods more efficient, the engineering team designed and planned access roads so that large equipment, trucks and materials could be transported and unloaded.
Lineworkers are replacing the galvanized lattice steel structures with weathered steel monopoles from Meyer Utility Structures on double 138-kV vertically stacked circuits. The average height of the current towers is 93 ft, but the new monopoles average about 155 ft high. When increasing the height of the structures, DLC’s engineers consulted the National Electric Safety Code to ensure the monopoles met or exceeded all of the minimum clearance requirements. In addition, they reviewed severe weather cases to ensure the structures would be resilient and reliable, even in heavy snow or high winds.
In addition, transitioning from the towers to the new structures minimizes the footprint of the foundations and reduces inspection and maintenance costs due to fewer bolted connections and steel parts. The towers are wider and have four foundations each, but the new monopoles only have one foundation and a much smaller footprint. The overall inspection and maintenance needs over the new infrastructure’s lifetime is significantly reduced.
Another significant benefit of the weathering steel monopoles is that they do not need to be painted, unlike the lattice steel towers, which must be constantly painted to prevent corrosion. DLC has been replacing the towers with monopoles, not only on the BI-Crescent line, but also in other parts of its service territory. For example, in areas with hills, valleys and narrow spaces, the monopoles are the right solution for that kind of location and terrain.
The stacked circuits are also farther away from trees and other potentially harmful vegetation. The existing circuit has a side-by-side design, but with the monopoles, the circuits are stacked on top. Because all six wires and the shield wire are in a column, the wires are mostly above the treeline. That way, if a tree does fall near the structure, it will most likely miss the wires.