Photo by Sterlite Power.
Key Elements
- 178-km (111-mile), 400-kV double-circuit, quad-conductored Silchar-Misa transmission line with aluminum conductor steel-reinforced (ACSR) Moose conductor having an overall diameter of 31.77 mm (1.25 inches). This line provides a strong interconnection between the northern and southern parts of the Northeastern region, facilitating the dispersal of power from central, private generation projects to various parts of the region through the formation of a 400-kV Silchar-Misa-Balipur-Bongaigaon-Azara-Bymihat-Silchar ring network. Further, this transmission line provides an additional circuit beyond Silchar for the evacuation of power from the Palatana gas-based power plant.
- 132-kV double-circuit Biswanath Chariyali-Itanagar transmission line with ACSR Panther conductor having an overall diameter of 28.62 mm (1.13 inches). This transmission line strengthens the interconnections between Assam and Arunachal Pradesh by providing an additional source of power for the city of Itanagar.
132-kV double-circuit transmission line between the Agartala gas turbine power plant (AGTPP) owned by the North East Electric Power Corp. (NEEPCO) and PK Bari was upgraded with high-temperature, low-sag (HTLS) conductor having a diameter of 18.06 mm (0.711 inches). This 84-km (52-mile) transmission line was planned
for the reliable evacuation of power from the AGTPP generation power plant, which has an installed generation capacity of 135 MW. - 400-kV Surajmaninagar-PK Bari double-circuit transmission line with ACSR Moose conductor having an overall diameter of 31.77 mm (1.25 inches). This is 77-km
(48-mile) transmission line provides an additional 400-kV corridor to enable reliable power evacuation from the Pallatana gas turbine power plant. - Two 400/132-kV greenfield substations — each equipped with two sets of three single-phase 105-MVA, 400/132-kV transformers — providing transformation capacity of 315 MVA each, for a total of 630 MVA. One single-phase 105-MVA transformer is supplied as a spare unit. The substations are located at Surajmaninagar and PK Bari in the state of Tripura. Each substation has sufficient space to install one additional set of three single-phase 105-MVA, 400/132-kV transformers, for additional future capacity of 315 MVA. This element of the overall project was subject to an engineering, procurement and construction (EPC) contract undertaken in partnership with General Electric.